Summary of lecture notes from the Project Management course at Universiteit Gent's Master of Business Engineering (Operations Management) program. Covers baseline scheduling fundamentals including PERT methodology with three-point estimation, CPM network analysis, and project phase structure (definition, scheduling, execution, control). Topics include the project triangle trade-offs, Work Breakdown Structure (WBS), Activity-on-Node (AON) vs Activity-on-Arc (AOA) networks, forward/backward pass scheduling, and critical path analysis with practical examples. Essential reference material for understanding deterministic scheduling in low complexity/low risk projects and preparing for project management assessments.

Voorbeeld van de inhoud

1. Introduction
A project is a temporary endeavor with a defined beginning and end, undertaken to meet unique
goals and objectives and to create beneficial or added value. The classic project triangle shows
the trade-off between cost, time and specifications, where improving one dimension typically
affects the others

Scheduling covers all static planning work done before project execution, whereas control
refers to dynamic activities during project progress.
Risk analysis forms a feedback loop between scheduling and control: risk is analyzed in advance
in a static way, while actual risk happens during the dynamic execution phase.

Project mapping positions projects along two axes: complexity (resources) and uncertainty
(risk).

• Low uncertainty and low complexity lead to baseline scheduling with
PERT/CPM. Example: Fabricom: luggage systems, 5-6 people, no huge risk.

• High risk and low complexity lead to Scheduling Risk Analysis (SRA). Example:
Brabantia, 3-4 people, marketing success defined at the end = risk.

• High complexity and low risk point to Critical Chain scheduling (CC). Example: Water
infrastructure.

• High complexity and high risk lead to Critical Chain/Buffer Management (CC/BM),
where buffers are added to protect against risk. Example: NPD, development iPhone: no
idea what to expect at the end of the project.


2. Baseline Scheduling
2.1. PERT basics
PERT (Program Evaluation and Review Technique) uses three time estimates for each activity: a
(best), m (realistic), and b (worst). Activity durations are assumed to follow a right-skewed beta
distribution, closer to the worst case than to the best case.

Formulas:

• Expected duration: (𝑎 + 4𝑚 + 𝑏)/6

• Standard deviation: (𝑏 − 𝑎)/6

The procedure is:

1. Define three time estimates per activity.

2. Compute average and standard deviation per activity.

3. Determine the average critical path duration.

4. Apply the Central Limit Theorem to approximate total project duration.

5. Use statistical insight to support decisions.

, 2.1.1. Strengths & Weaknesses
Average of CPM close to 50/50, but actual 44/56 (error is low)

• Estimates are human input (3 estimates better than 1, “garbage in, garbage out”)
• Simplifications of statistics (assumption no correlation: standard deviation)
• PERT ignores non-critical activities (can become critical -> stdev & CLT not correct)

2.2. CPM and the project phases
CPM (Critical Path Method) focuses on deterministic durations and is especially suited to low
complexity, low risk projects. Capacity increase (new water towers, pipeline, machines,
buildings): not easy but not extremely complex.

The logic of phases:

• Concept →

• Definition (what?), static →

• Scheduling (when?), static →

• Execution, dynamic (Mister Murphy) →

• Control →

• Termination.

In the definition phase, a global plan is prepared, including:

• A(1): determination of activities via a Work Breakdown Structure (WBS)

• P(2): responsibility assignment (possibly external experts)

• L(3): sequencing and linking of activities

• N(4): network analysis providing input for scheduling tools (output of definition phase)

The WBS breaks down the project objective into

• Root node
• Work items (building machines, define work items -> expertise) (not only 1/WI)
• Work packages
• Activities

Where the lowest level corresponds to the highest level of detail; each level has a specific
functionality.
This is related to the Organization Breakdown Structure (OBS): project objective → work items
→ work packages → activities.
VMW definition phase with two parts (reservoir and new machines) due to different objectives
(time vs cost).

Part1: increase reservoir: very urgent, more water during peak needed now!!: obj = time
Part2: new machines for bigger capacity not so urgent (more demand only in 6-7 years) obj: cost

Documentinformatie

Geüpload op
28 april 2026
Aantal pagina's
12
Geschreven in
2025/2026
Type
Samenvatting
€5,99

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kan je een ander document kiezen. Je kan het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Verkocht
0
Volgers
0
Items
2
Laatst verkocht
-



Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via Bancontact, iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo eenvoudig kan het zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen