ACG CXA 2026 EVALUATION EXAMS QUESTIONS AND
ANSWERS SURE A+
✔✔commissioning benefits - ✔✔■ Reduction of change orders and additional claims
Fewer project delays
■ Managed start-up requirements
■ Shorter building turn-over transition period
■ Less post-occupancy corrective work
■ Minimized effects from design changes
■ Improved indoor air quality and occupant productivity
■ Better operation, maintenance and reliability
■ Lower energy and operations costs
■ Value-added quality construction
■ Complete and useful O&M documentation
■ Owner advocacy for design and construction decisions
■ Documentation of the entire construction process

✔✔commissioning authority - ✔✔leader of the commissioning team

✔✔Important qualifications and skills of HVAC Commissioning Agencies include: - ✔✔■
Knowledge of HVAC systems, covering design, common control strategies, installation,
operations and maintenance
■ Experience in controls for HVAC systems, including familiarity with current
technology, both conventional and direct digital control
■ Practical field construction background
■ Demonstrated ability to organize many specific activities into a coherent
commissioning plan
■ Communications skills, both written and verbal
■ Profi ciency in documentation
■ Experience working with multi-disciplinary teams
■ Familiarity with testing and balancing

✔✔overall cost of comprehensive HVAC commissioning - ✔✔usually between 2% and
5% of the HVAC construction cost

✔✔overall cost of construction HVAC commissioning - ✔✔approximately 80% of that for
comprehensive commissioning

✔✔typically follows the RFQ process - ✔✔An interview process, a Request for Proposal
(RFP) process, and contract negotiations

✔✔RFQ should contain the following information: - ✔✔■ Date of Issuance
■ RFQ Due Date
■ Owner/Program Manager Contact Information
■ Project/Program Description

,■ Project/Program Schedule
■ Small Business/Minority Business Participation Goals
■ Characterization of the Request
■ Qualification Requirements
■ RFQ and Selection Process Description
■ Selection Criteria
■ Notification of Selection/Unsuccessful Respondent Protocol

✔✔RFP should contain the following information: - ✔✔■ Date of Issuance
■ RFP due date
■ Owner/program manager contact information
■ Project name and location
■ Project/program description
■ Project/program schedule
■ Small Business/Minority Business participation goals
■ Characterization of the request
■ Qualification requirements
■ RFQ and selection process description
■ Selection criteria
■ Notification of selection/unsuccessful respondent protocol
■ Approximate size, use and occupancy of the facility
■ Types of systems to be commissioned
■ Special project considerations
■ Design team identification
■ Design and construction document development and distribution process
■ Submittal requirements
■ Request for scope of proposed services
■ Request for cost of services
■ Detailed break-out of services costs
■ Hourly charge-out rates for services applying to duly authorized extra work
■ Interview or pre-proposal conference schedules
■ Restrictions on communications with selection team members
■ Rules of withdrawal
■ Non-collusion affidavit
■ Insurance requirements
■ Contract requirements

✔✔The commissioning authority must possess... - ✔✔organizational, documentation,
communications, and team-building skills

✔✔The preferred delivery model for commissioning services advocated by ACG. -
✔✔Independent certified commissioning authority under direct contract to the owner

✔✔The AABC Commissioning Group (ACG) was established in... - ✔✔2004 as a
separate non-profit association

, ✔✔AIA - ✔✔registered architect

✔✔PE - ✔✔professional engineer

✔✔the heart of the commissioning process - ✔✔functional performance testing

✔✔responsibility of CxA during FPT - ✔✔directing, witnessing, and documenting the
tests

✔✔certifies TBEs - ✔✔Associated Air Balance Council (AABC)

✔✔the hallmark of both AABC and ACG - ✔✔independence

✔✔TBEs - ✔✔independent and possess the technical expertise to carry out both HVAC
functional performance testing and TAB services

✔✔the members of an HVAC Commissioning Team from the construction phase until
the end of the project may include representatives of the following: - ✔✔■ owner
■ end-user
■ architect
■ mechanical engineer
■ electrical engineer
■ commissioning authority
■ mechanical contractor
■ electrical contractor
■ controls contractor
■ sheet metal contractor
■ TAB agency
■ owner's O&M staff
■ general contractor (or construction manager)

✔✔Pre-Design - ✔✔■ Commissioning is established as an integral part of the
project
■ The owner selects the commissioning authority
■ Develop the scope of commissioning
■ Commissioning authority reviews design intent document

✔✔Design - ✔✔■ Review design to ensure it accommodates commissioning
■ Write commissioning specifications defining contractor responsibilities
■ Commissioning authority writes the commissioning plan
■ Establish the project schedule

✔✔Construction - ✔✔■ Commissioning authority reviews contractor submittals
■ Commissioning authority updates commissioning plan

Infos sur le Document

Publié le
12 juin 2026
Nombre de pages
19
Écrit en
2025/2026
Type
Examen
Contenu
Questions et réponses
18,18 €

Mauvais document ? Échangez-le gratuitement Dans les 14 jours suivant votre achat et avant le téléchargement, vous pouvez choisir un autre document. Vous pouvez simplement dépenser le montant à nouveau.
Rédigé par des étudiants ayant réussi
Disponible immédiatement après paiement
Lire en ligne ou en PDF

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
EXAMCAFE
3,4
(19)
Vendu
154
Abonnés
7
Éléments
26056
Dernière vente
1 semaine de cela



Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Vous travaillez sur vos références ?

Créez des citations précises en APA, MLA et Harvard avec notre générateur de sources gratuit.

Vous travaillez sur vos références ?

Foire aux questions