ACG CXA FINAL EXAM ACTUAL QUESTIONS AND
ANSWERS SURE A+
✔✔What is the objective of scheduling Commissioning Process activities? - ✔✔To
integrate and coordinate with other Construction Phase activities and to allow all
Commissioning Team members to plan their work to achieve the OPR.

✔✔Commissioning activities (should / should not) be integrated into the construction
schedule. - ✔✔Should

✔✔What is the primary method used during the Construction Phase to verify that the
installed systems and assemblies comply with the OPR? - ✔✔Site visits

✔✔When does the Occupancy and Operations Phase (i.e. Post-Acceptance Phase)
begin? - ✔✔At substantial completion

✔✔At a minimum, when does the Occupancy and Operations Phase (i.e. Post-
Acceptance Phase) end? - ✔✔Through the contractual warranty/correction period

✔✔What are the two primary documentation requirements for the Construction Phase
Commissioning Process? - ✔✔1.) Construction Phase Commissioning Process Report
2.) Commissioning elements of the Systems Manual

✔✔What phase is the final project Systems Manual completed? - ✔✔The Occupancy
and Operations Phase

✔✔What are the two primary documentation requirements for the Occupancy and
Operations Phase? - ✔✔1.) Final project Cx Process Report
2.) Final project Systems Manual

✔✔What phase are the Owner training requirements developed? - ✔✔Pre-Design
Phase

✔✔What phase is the commissioning team formed? - ✔✔Pre-Design Phase

✔✔What phase is the OPR developed? - ✔✔Pre-Design Phase

✔✔What phase is the initial Cx Plan developed? - ✔✔Pre-Design Phase

✔✔What phase are design reviews performed? - ✔✔Design Phase

✔✔What phase is the OPR and BOD verified? - ✔✔Design Phase

,✔✔What phase are submittals reviewed and verified? - ✔✔Construction Phase

✔✔What phase are test procedures (FPTs) developed? - ✔✔Construction Phase

✔✔What phase is the systems manual verified? - ✔✔Construction Phase

✔✔What phase are construction checklist verified? - ✔✔Construction Phase

✔✔What phase are functional tests implemented? - ✔✔Construction Phase

✔✔What phase is seasonal testing performed? - ✔✔Occupancy and Operations Phase

✔✔What phase is the warranty review? - ✔✔Occupancy and Operations Phase

✔✔What phase is the systems manual outline-expanded? - ✔✔Design Phase

✔✔Who is responsible for Pre-Deisgn Phase Document Control - ✔✔CxA

✔✔Who is responsible for Pre-Deisgn Phase Develop Cx Scope - ✔✔CxA

✔✔Who is responsible for Pre-Deisgn Phase Review DID/OPR - ✔✔CxA

✔✔Who is responsible for Pre-Deisgn Phase Prepare Cx Outline - ✔✔CxA

✔✔Who is responsible for Pre-Deisgn Phase Attend Meetings - ✔✔CxA

✔✔Who is responsible for Deisgn Phase Document Control - ✔✔CxA

✔✔Who is responsible for Deisgn Phase Identify Systems to Cx - ✔✔CxA

✔✔Who is responsible for Deisgn Phase Design Reviews - ✔✔CxA

✔✔Who is responsible for Deisgn Phase Review Cx Specifications - ✔✔CxA

✔✔Who is responsible for Deisgn Phase Design Phase Cx Plan - ✔✔CxA

✔✔Who is responsible for Deisgn Phase Design Phase Kick-Off Meeting - ✔✔Shared

✔✔Who is responsible for Deisgn Phase Draft SVCs - ✔✔Shared

✔✔Who is responsible for Deisgn Phase Draft FPTs - ✔✔Shared

✔✔Who is responsible for Deisgn Phase Attend Meetings - ✔✔CxA

,✔✔Who is responsible for Deisgn Phase Attend Pre-Bid Meeting - ✔✔CxA

✔✔Who is responsible for Construction Phase Pre-Construction Meeting - ✔✔Shared

✔✔Who is responsible for Construction Phase Document Control - ✔✔CxA

✔✔Who is responsible for Construction Phase Construction Cx Plan - ✔✔CxA

✔✔Who is responsible for Construction Phase Cx Schedule Integration - ✔✔CxA

✔✔Who is responsible for Construction Phase Pre-TAB Report Review - ✔✔CxA

✔✔Who is responsible for Construction Phase Review Submittals - ✔✔CxA

✔✔Who is responsible for Construction Phase Update SVCs - ✔✔CxT

✔✔Who is responsible for Construction Phase Approve SVC Updates - ✔✔CxA

✔✔Who is responsible for Construction Phase Approve SVCs - ✔✔CxA

✔✔Who is responsible for Construction Phase Distribute SVCs - ✔✔CxT

✔✔Who is responsible for Construction Phase Update FPTs - ✔✔CxT

✔✔Who is responsible for Construction Phase Approve FPTs - ✔✔CxA

✔✔Who is responsible for Construction Phase Approve FPT Updates - ✔✔CxA

✔✔Who is responsible for Construction Phase Distribute FPTs - ✔✔CxT

✔✔Who is responsible for Construction Phase Site Observations - ✔✔CxT

✔✔Who is responsible for Construction Phase Write SPQC Reports - ✔✔CxT

✔✔Who is responsible for Construction Phase Approve SPQC Reports - ✔✔CxA

✔✔Who is responsible for Construction Phase Distribute SPQC Reports - ✔✔CxT

✔✔Who is responsible for Construction Phase Create RTFs - ✔✔CxA

✔✔Who is responsible for Construction Phase Approve RTFs - ✔✔CxA

, ✔✔Who is responsible for Construction Phase Distribute RTFs - ✔✔CxT

✔✔Who is responsible for Construction Phase Coordination Meetings - ✔✔CxT

✔✔Who is responsible for Construction Phase Progress Meetings - ✔✔CxT

✔✔Who is responsible for Construction Phase Attend Meetings - ✔✔Shared

✔✔Who is responsible for Construction Phase Supervise/Direct CxT - ✔✔CxA

✔✔Who is responsible for Construction Phase Verify SVC Completion/Spot-Check SVC
Accuracy - ✔✔CxT

✔✔Who is responsible for Construction Phase Witness Install Tests - ✔✔CxT

✔✔Who is responsible for Construction Phase Monitor Controls Install - ✔✔CxT

✔✔Who is responsible for Construction Phase Monitor TAB Execution - ✔✔CxT

✔✔Who is responsible for Construction Phase Facilitate Start-Up of Commissioned
Systems - ✔✔CxT

✔✔Who is responsible for Construction Phase Collect Manuf. Checklists - ✔✔CxT

✔✔Who is responsible for Construction Phase Cx Schedule Updates - ✔✔CxA

✔✔Who is responsible for Construction Phase Review "As-Built" Record - ✔✔Shared

✔✔Who is responsible for Construction Phase Review O&M Documents - ✔✔CxT

✔✔Who is responsible for Construction Phase Facilitate O&M Training - ✔✔CxT

✔✔Who is responsible for Construction Phase Track RFI's/CO's/SI's - ✔✔CxT

✔✔Who is responsible for Construction Phase Monitor Project Team Field Reports -
✔✔CxT

✔✔Who is responsible for Construction Phase Document Control - ✔✔CxA

✔✔Who is responsible for Acceptance Phase Controls P to P Review - ✔✔CxT

✔✔Who is responsible for Acceptance Phase Control Program Review - ✔✔CxT

Infos sur le Document

Publié le
12 juin 2026
Nombre de pages
31
Écrit en
2025/2026
Type
Examen
Contenu
Questions et réponses
18,18 €

Mauvais document ? Échangez-le gratuitement Dans les 14 jours suivant votre achat et avant le téléchargement, vous pouvez choisir un autre document. Vous pouvez simplement dépenser le montant à nouveau.
Rédigé par des étudiants ayant réussi
Disponible immédiatement après paiement
Lire en ligne ou en PDF

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
EXAMCAFE
3,4
(19)
Vendu
154
Abonnés
7
Éléments
26056
Dernière vente
1 semaine de cela



Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Vous travaillez sur vos références ?

Créez des citations précises en APA, MLA et Harvard avec notre générateur de sources gratuit.

Vous travaillez sur vos références ?

Foire aux questions