Examen
PMT 0170 Risk Management
- Cours
- Établissement
Why are Monte Carlo simulations used in program schedule analysis? 10.2 - Answer- To find the cumulative effect of multiple risks on total project schedule duration or total project cost A shortage of steel has caused a delay in one of the tasks until the material is available. The original plan...
[Montrer plus]