- Guías de estudio, Notas de estudios & Resúmenes
¿Buscas las mejores guías de estudio, notas de estudio y resúmenes para ? En esta página encontrarás 7 documentos de estudio para .
7 resultados
Examen
CSI CDT Study info Questions and Answers 100% Solved
CSI CDT Study info Questions and Answers 
100% Solved 
Drawings Graphic and textural information organized in a two dimensional surface for the 
purpose of conveying data about a specific portion of a project. 
Non Scaled Views diagrams, key plans, schedules, perspectives, isometric, and title sheet 
drawings 
Scaled Views Include orientations in the horizontal plane and in the vertical cuts through 
the project
Examen
CSI - CDT study terms. Questions and Answers 100% Solved
PopularCSI - CDT study terms. Questions and 
Answers 100% Solved 
Hard Cost Site acquisition, surveys, preparation 
Construction 
FFE 
Construction Budgets 1 Cost per measured unit 
2 Component cost 
3 Systems
Examen
CSI CDT Exam Questions with Correct Answers
CSI CDT Exam Questions with Correct 
Answers 
Total Project Commissioning Quality process utilizing an independent company 
providing services. Commissioning continues through the construction stage of the project to 
provide QA/QC. 
Life Cycle Costs Total cost of ownership. Initial construction costs as well as renovation, 
remodeling, and improvements.
Examen
CSI CDT Questions with Correct Answers
CSI CDT Questions with Correct Answers 
When is the CSI/CSC UniFormat most often used? 
a. During project conception and schematic design 
b. In the procurement stage 
c. In the facility management phase 
d. Throughout the project life cycle, to organize information by materials and methods a. 
During project conception and schematic design
Examen
CSI CDT Mock Exam Questions with Correct Answers
CSI CDT Mock Exam Questions with 
Correct Answers 
The cost of materials plus and additional fee of overhead and profit. (Fee Negotiated), a GMP 
(Guaranteed Maximum Price), shared savings (Split % 60/40 of Savings) and incentives for early 
completion(Bonus) may all be part of a negotiated "Cost-Plus Fee". 
Ref PDPG 7.1.6.3 
Change Orders are: 
A. Prepared by the Contractor. 
B. Prepared by the Architect/Engineer. 
C. Prepared by the Owner. 
D. Prepared by any of the above. B. Prepared...
Examen
CSI CDT: Module 5 Questions and Answers 100% Solved
CSI CDT: Module 5 Questions and Answers 
100% Solved 
Define: Notice of Award The owner may issue a notice of award if preparation of the 
actual contract might be delayed. This procedure is required when a challenge period is required 
by statute. A notice of award establishes the beginning of the challenge period. (PDPG 11.5.2.4) 
Define: Contract Agreement The written document signed by each party and is the legal 
instrument binding the parties to the contract. The agreement defines the ...
Examen
CSI CDT Exam Questions with Correct Answers
CSI CDT Exam Questions with Correct 
Answers 
How to select contract services Lowest competitive bidder, reputation, previous 
relationship with the Owner, or primary selection methods 
Project Variables Allowances 
Alternates 
Unit Prices 
used to control: 
-indeterminate items, unknowns, and contingencies 
-postponement of decisions until more information is known (i.e. cost) 
-identification and control of construction costs