Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 3 fuera de 26 páginas
Examen

AK Electrical Administrator – Linework Exam Questions And Correct Answers (Verified Answers) Plus Rationale 2026 Q&A| Instant Download Pdf

Document preview thumbnail
Vista previa 3 fuera de 26 páginas

AK Electrical Administrator – Linework Exam Questions And Correct Answers (Verified Answers) Plus Rationale 2026 Q&A| Instant Download Pdf

Vista previa del contenido

AK Electrical Administrator –
Linework Exam Questions And Correct
Answers (Verified Answers) Plus
Rationale 2026 Q&A| Instant Download
Pdf

1.

What is the minimum approach distance for qualified lineworkers working
near 15 kV lines?
A. 2 feet
B. 3 feet
C. 4 feet
D. 5 feet
Rationale: OSHA and industry standards set a 4-ft MAD for up to 15 kV.

2.

Which device is used to protect distribution lines from overcurrent events
caused by faults?
A. Recloser
B. Fuse cutout
C. Breaker
D. All of the above
Rationale: All listed devices provide overcurrent protection at various
system points.

3.

,A guy wire must be insulated when installed across:
A. Roads
B. Railroads
C. Communication lines
D. Parking lots
Rationale: Guy wire insulators prevent dangerous potentials from traveling
into comms systems.

4.

What is the typical frequency of AC power in North American utility
systems?
A. 25 Hz
B. 60 Hz
C. 100 Hz
D. 120 Hz
Rationale: Standard utility frequency is 60 Hz.

5.

Which conductor configuration minimizes corona on high-voltage lines?
A. Single-strand copper
B. Bundled conductors
C. ACSR only
D. Parallel bare wires
Rationale: Bundled conductors reduce electric field intensity and corona
formation.

6.

What must be done before grounding a de-energized line?
A. Test weather conditions
B. Test the line for absence of voltage
C. Check crew size
D. Contact customers
Rationale: Always test-before-touch to ensure the line is de-energized.

7.

, The primary purpose of a line recloser is to:
A. Regulate voltage
B. Automatically clear temporary faults
C. Ground the system
D. Reduce harmonics
Rationale: Reclosers isolate temporary faults to maintain service
continuity.

8.

What is the typical phase-to-phase voltage of a 7.2/12.47-kV system?
A. 7.2 kV
B. 12.47 kV
C. 24.9 kV
D. 14.4 kV
Rationale: 7.2 is phase-neutral; 12.47 kV is phase-to-phase.

9.

A bucket truck operator must maintain a minimum clearance of _____ from
energized 34.5-kV conductors.
A. 4 ft
B. 6 ft
C. 10 ft
D. 12 ft
Rationale: OSHA minimum for 34.5 kV is 10 ft.

10.

A transformer with a 5-kVA rating and 120-V secondary can deliver what
maximum current?
A. 20 A
B. 41.7 A
C. 60 A
D. 83.3 A
Rationale: I = 5000/120 ≈ 41.7 A.

Información del documento

Subido en
8 de diciembre de 2025
Número de páginas
26
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$22.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
PrepPal1
4.0
(25)
Vendido
109
Seguidores
6
Artículos
4661
Última venta
1 semana hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes