CM 3111 Module 4 Quiz Construction Estimating (Grade 80.00 out of
100.00) 2025-2026 Louisiana State University
Module 4 Quiz
Status Finished
Started Saturday, November 15, 2025, 2:13 PM
Completed Saturday, November 15, 2025, 2:17 PM
Duration 4 mins 12 secs
Points 8.00/10.00
Grade 80.00 out of 100.00
Question 1
Correct1.00 points out of 1.00Flag question
Question text
How are stone veneer quantities estimated?
Question 1Answer
a.
cubic yard
b.
linear foot
c.
none of the above
d.
area
Feedback
The correct answer is: area
Question 2
, Correct1.00 points out of 1.00Flag question
Question text
Structural metals are purchased by the:
Question 2Answer
a.
ton
b.
linear footage
c.
none of the above
d.
square footage
Feedback
The correct answer is: ton
Question 3
Correct1.00 points out of 1.00Flag question
Question text
The amount of time required for a mason to lay a masonry unit varies with
the:
Question 3Answer
a.
Size
100.00) 2025-2026 Louisiana State University
Module 4 Quiz
Status Finished
Started Saturday, November 15, 2025, 2:13 PM
Completed Saturday, November 15, 2025, 2:17 PM
Duration 4 mins 12 secs
Points 8.00/10.00
Grade 80.00 out of 100.00
Question 1
Correct1.00 points out of 1.00Flag question
Question text
How are stone veneer quantities estimated?
Question 1Answer
a.
cubic yard
b.
linear foot
c.
none of the above
d.
area
Feedback
The correct answer is: area
Question 2
, Correct1.00 points out of 1.00Flag question
Question text
Structural metals are purchased by the:
Question 2Answer
a.
ton
b.
linear footage
c.
none of the above
d.
square footage
Feedback
The correct answer is: ton
Question 3
Correct1.00 points out of 1.00Flag question
Question text
The amount of time required for a mason to lay a masonry unit varies with
the:
Question 3Answer
a.
Size