BYU CM 415 PROJECT MANAGEMENT STUDY GUIDE

Vista previa del contenido

BYU CM 415 PROJECT MANAGEMENT STUDY GUIDE

Definition of Project Management - Answer -A system that provides for the Planning,
Organizing, Directing Controlling (PODC) of a unique one time activity. So as to
complete on time, on budget, safely, to a specific quality with no claims.

Define Project - Answer -A unique one time activity with tasks and a fixed duration

DBB - Answer -Design-Bid-Build

DB - Answer -Design - Build

GMP - Answer -Cost+Guaranteed Max Price

CM @ Risk - Answer -CM is involved early like in DB, but they are not one entity

IPD - Answer -Integrated Project Delivery

PPP - Answer -Public Private Partnership

CM Agency - Answer -CM (owner's rep) is the buffer between the Arch and General
Cont.

LMESO - Answer -Labor, Materials, Equipment, Subs, Other

Project Manager Acts as the... - Answer -Coach

Why is Scope important? - Answer -Because it is basically relevance.

Why is Schedule important? - Answer -It pushes workers to complete work on time, but
rarely works

Why is Resources important? - Answer -If the owner isn't worried about cost, then
scope and schedule can be made less important.

Why is Quality important? - Answer -The quality of work is as important as the owner
wishes.

What is the Most important meeting? - Answer -Pre-Construction. Because you set the
expectations.

Meeting Minutes? - Answer -Assignments and Decisions
Attendance
Date, Time, Place
Old items, new business

, RFI's
Schedule, progress

What % of Projects meet the Project Management Definition? - Answer -20%

Project Team Members and responsibilites - Answer -Owner - Pays the $
Architect - designs the projects (referee)
Contractor - Provides the LMESO
Inspectors - 4 way, concrete, rebar, etc
Project Manager - (Coach) - PODC / Manage Risk
Superintendent - face of project onsite / responsible for physical building production
Project Engineer - RFIs, COs, Document Project, Know everything about project.
Field Engineer - Out of field doing quality check

Goals of Staffing - Answer -• Right number of people
• Assign each player to position he fits best
• Select each person on the basis of his/her combined skills, abilities, and attitude
• Design the team so that each person's weakness is balanced by another's strengths
• Create a real team where - people think and work well together. Avoid a group where
one superstar dominates and everyone else is secondary

Construction Documents - Answer -Document Log - Track changes / Back up company
against allegations
Subcontracts - written agreement between cont. and sub
Contract docs -
Project docs-
In house docs -
Daily Logs -
As Built Drawings -
Labor Agreement -
Letter of Intent -
Purchase Orders -
RFI -
Submittals -
Change Orders -
Detail Report -
Job Cost Projection Report -

As-Built Drawings - Answer -Convey the correct information as the project is being
constructed.

The Superintendant is in charge
**MEP as-builts
**Underground (Utility) As-builts

What is an Addenda? - Answer -A change to the contract BEFORE the bid.

Información del documento

Subido en
12 de noviembre de 2025
Número de páginas
9
Escrito en
2025/2026
Tipo
Otro
Personaje
Desconocido
$14.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
GEEKA
3.8
(376)
Vendido
2225
Seguidores
1451
Artículos
62880
Última venta
9 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes