What is the key benefit of the Executing Process Group? - Answer- The work needed to
meet the project requirements and objectives is performed according to plan
Which of the following are included in approved change requests? - Answer-
Modifications to the terms and conditions of the contract
An output of the Control Resources process is: - Answer- Work performance information
What are the four processes in Project Stakeholder Management? - Answer- Identify
Stakeholders, Plan Stakeholder Engagement, Manage Stakeholder Engagement, and
Monitor Stakeholder Engagement
What is calculated using a percentage of the estimated activity duration, or a fixed
number of work periods? - Answer- Contingency reserve
At what point(s) in the project is the Monitor Stakeholder Engagement process
performed? - Answer- The process is performed throughout the project
Examples of interpersonal skills that a project manger uses during Manage Stakeholder
Engagement include each of the following: - Answer- Political awareness
Negotiation
Conflict management
Which of the following is the most commonly used type of precedence relationship when
using the precedence diagramming method (PDM)? - Answer- Finish- to- start (FS)
Which type of float is described as the amount of time that a schedule activity can be
delayed or extended from its early start date without delaying the project finish date or
violating a schedule constraint? - Answer- Total Float
Which is a definition of statement of work (SOW)? - Answer- A narrative description of
products, services, or results to be delivered by the project.
Which of the following are examples of source selection criteria? - Answer- Delivery
dates and financial stability
,Risk transference nearly often involves: - Answer- Payment of a risk premium to the
party taking on the risk
Why is project tailoring necessary? - Answer- Each project is unique
Benchmarking involves comparing actual or planned project practices to those of
comparable projects with all of the following characteristics EXCEPT: - Answer- To
provide a basis for measuring performance
Which of the following is an input of the Control Scope process? - Answer- Work
performance data
What is the key benefit of managing project knowledge? - Answer- Prior knowledge is
leveraged to improve outcomes and knowledge crated is available to support future
projects
What is the key benefit of the Closing Process Group? - Answer- Phases, projects, and
contracts are closed out appropriately
All of the following are true about the statement of work (SOW) for a procurement
EXCEPT: - Answer- It can be ambiguous or incomplete for future negotiations
Which of the following includes all costs incurred over the life of the product by
investment in preventing non conformance to requirements, appraisal of the product or
service for conformance to requirements, and failure to meet requirements? - Answer-
Cost of Quality (COQ)
Project Scope Management includes which of the following? - Answer- Processes
required to ensure that the project includes all the work required -and only the work-
required to complete the project successfully
The collection of generally sequential and sometimes overlapping project phases,
whose name and number are determined by the management and control the needs of
the organizations or organizations involved in the project, is known as the: - Answer-
Project life cycle
What tasks should be part of the scope management plan? - Answer- Define a strategy
for handling scope change requests and create a work breakdown structure (WBS)
Which of the following are considerations for the tailoring for project schedule
management? - Answer- Life Cycle approach, resource availability, and project
dimensions
The cost management plan has all of the following characteristics EXCEPT: - Answer- It
is based on project cost estimates and is seperate from the project management plan
, Your sponsor specifies that there is no additional money in the budget for your project
and asks you to complete the project at the original budget at completion (BAC). To
achieve that goal, you and your team must complete the remaining work at the to-
complete performance index (TCPI) of
BAC= 200
PV= 100
AC=120
EV= 80 - Answer- 1.50
TCPI equation: - Answer- (BAC - EV) / (BAC - AC)
which of the following most accurately describes the quantitative assessments of the
probable costs required to complete project work, as well as contingency amounts to
account for identified risks and management reserve to cover unplanned work? -
Answer- Cost Estimates
When tailoring processes for Project Quality Management, you should consider all
these. - Answer- Policy compliance and auditing
Stakeholder Engagement
Standards and regulatory compliance
Change requests are processed for review and disposition through the Perform
Integrated Change Control process and may include which of the following types of
change activities? - Answer- Preventive action
What is a formal proposal to modify a document, deliverable, or baseline? - Answer-
Change Request
Which of the following is a form of project life cycle that may also be referred to as
waterfall life cycle?
Project Life Cycle
Product Life Cycle
Predictive Life Cycle
Adaptive Life Cycle - Answer- Predictive Life Cycle
Which project schedule model displays start and end dates, as well as expected
durations? - Answer- Bar Charts
CORRECT ANSWERS
What is the key benefit of the Executing Process Group? - Answer- The work needed to
meet the project requirements and objectives is performed according to plan
Which of the following are included in approved change requests? - Answer-
Modifications to the terms and conditions of the contract
An output of the Control Resources process is: - Answer- Work performance information
What are the four processes in Project Stakeholder Management? - Answer- Identify
Stakeholders, Plan Stakeholder Engagement, Manage Stakeholder Engagement, and
Monitor Stakeholder Engagement
What is calculated using a percentage of the estimated activity duration, or a fixed
number of work periods? - Answer- Contingency reserve
At what point(s) in the project is the Monitor Stakeholder Engagement process
performed? - Answer- The process is performed throughout the project
Examples of interpersonal skills that a project manger uses during Manage Stakeholder
Engagement include each of the following: - Answer- Political awareness
Negotiation
Conflict management
Which of the following is the most commonly used type of precedence relationship when
using the precedence diagramming method (PDM)? - Answer- Finish- to- start (FS)
Which type of float is described as the amount of time that a schedule activity can be
delayed or extended from its early start date without delaying the project finish date or
violating a schedule constraint? - Answer- Total Float
Which is a definition of statement of work (SOW)? - Answer- A narrative description of
products, services, or results to be delivered by the project.
Which of the following are examples of source selection criteria? - Answer- Delivery
dates and financial stability
,Risk transference nearly often involves: - Answer- Payment of a risk premium to the
party taking on the risk
Why is project tailoring necessary? - Answer- Each project is unique
Benchmarking involves comparing actual or planned project practices to those of
comparable projects with all of the following characteristics EXCEPT: - Answer- To
provide a basis for measuring performance
Which of the following is an input of the Control Scope process? - Answer- Work
performance data
What is the key benefit of managing project knowledge? - Answer- Prior knowledge is
leveraged to improve outcomes and knowledge crated is available to support future
projects
What is the key benefit of the Closing Process Group? - Answer- Phases, projects, and
contracts are closed out appropriately
All of the following are true about the statement of work (SOW) for a procurement
EXCEPT: - Answer- It can be ambiguous or incomplete for future negotiations
Which of the following includes all costs incurred over the life of the product by
investment in preventing non conformance to requirements, appraisal of the product or
service for conformance to requirements, and failure to meet requirements? - Answer-
Cost of Quality (COQ)
Project Scope Management includes which of the following? - Answer- Processes
required to ensure that the project includes all the work required -and only the work-
required to complete the project successfully
The collection of generally sequential and sometimes overlapping project phases,
whose name and number are determined by the management and control the needs of
the organizations or organizations involved in the project, is known as the: - Answer-
Project life cycle
What tasks should be part of the scope management plan? - Answer- Define a strategy
for handling scope change requests and create a work breakdown structure (WBS)
Which of the following are considerations for the tailoring for project schedule
management? - Answer- Life Cycle approach, resource availability, and project
dimensions
The cost management plan has all of the following characteristics EXCEPT: - Answer- It
is based on project cost estimates and is seperate from the project management plan
, Your sponsor specifies that there is no additional money in the budget for your project
and asks you to complete the project at the original budget at completion (BAC). To
achieve that goal, you and your team must complete the remaining work at the to-
complete performance index (TCPI) of
BAC= 200
PV= 100
AC=120
EV= 80 - Answer- 1.50
TCPI equation: - Answer- (BAC - EV) / (BAC - AC)
which of the following most accurately describes the quantitative assessments of the
probable costs required to complete project work, as well as contingency amounts to
account for identified risks and management reserve to cover unplanned work? -
Answer- Cost Estimates
When tailoring processes for Project Quality Management, you should consider all
these. - Answer- Policy compliance and auditing
Stakeholder Engagement
Standards and regulatory compliance
Change requests are processed for review and disposition through the Perform
Integrated Change Control process and may include which of the following types of
change activities? - Answer- Preventive action
What is a formal proposal to modify a document, deliverable, or baseline? - Answer-
Change Request
Which of the following is a form of project life cycle that may also be referred to as
waterfall life cycle?
Project Life Cycle
Product Life Cycle
Predictive Life Cycle
Adaptive Life Cycle - Answer- Predictive Life Cycle
Which project schedule model displays start and end dates, as well as expected
durations? - Answer- Bar Charts