Examen

Isom 300 - Test 1 Questions & Answers|| 2025 Latest Update|| Verified A+

Document preview thumbnail
Vista previa 2 fuera de 6 páginas

What is a project? - ANSWERA temporary endeavor undertaken to create a unique product, service, or result. What are the main characteristics of a project? - ANSWER- an established objective - defined life span with a beginning and an end - usually, it has interdisciplinary involvement -typically doing something new - specific time, cost, and performance requirements

Vista previa del contenido

ISOM 300 - TEST 1 QUESTIONS &
ANSWERS|| 2025 LATEST UPDATE||
VERIFIED A+
What is a project? - ANSWERA temporary endeavor undertaken to create a unique
product, service, or result.

What are the main characteristics of a project? - ANSWER- an established objective
- defined life span with a beginning and an end
- usually, it has interdisciplinary involvement
-typically doing something new
- specific time, cost, and performance requirements

what are the 5 main project process groups (also known as project phases)? -
ANSWER- Initiating
- Planning
- Executing
- Monitoring
- Closing

Scope Statement - ANSWERPlanning process

Project Charter - ANSWERInitiating process

Analysis of project progress comparing cost baseline vs actual expenditure -
ANSWERMonitoring process

Stakeholder register - ANSWERInitiating process

What are the three groups/types of skills a Project manager should have? - ANSWER-
technical project management
- leadership
- strategic & business management

What is an Agile project management approach? - ANSWER-Deliver to customer ASAP
-Iterative: allows feedback on unfinished work
- Incremental: create deliverables throughout

What is a traditional project management approach? - ANSWER-Plan project in detail in
the beginning
-Deliver entire project to customer at end

, What is the difference between traditional and agile approach? - ANSWERAgile wants
to get product to customer as fast as they can. Traditional approach allows the project
to be fully completed before delivering to the customer.

What are the 3 organizational structures? - ANSWERfunctional, project, matrix

In which organizational structure does the project manager have a higher level of
authority? - ANSWERproject organization

In the matrix organizational structure does the functional manager have authority? Does
the project manager have authority? - ANSWERyes, and no

This company requires the independent development of each project. However, for an
efficient work the company should have different departments that are managed by their
own functional managers. What is the organizational structure of this company? -
ANSWERmatrix organization

Stakeholder - ANSWERIndividuals and organizations that are actively involved in a
project, or whose interests may be positively or negatively affected as a result of project
execution or completion. They may also exert influence over the project and its results.


John is the project manager of a project that has a specific completion date. After a
discussion with top management, the decisions made showed that while the completion
date is important, the cost is more important and a slip in the finish time would not be
acceptable if required to meet the cost targets. In this case, what would be the
classification in the priority matrix for the time and cost? - ANSWERtime = accept
cost = constrain

What is the objective of the communications plan? - ANSWER- stakeholder
identification and analysis
- communications vehicle

RACI Matrix - what does it mean to be responsible, accountable, consulted, and
informed? - ANSWER-R= responsible, those who do the work
-A=accountable, the one who has final approving authority
-C=consulted, those whose opinions are sought, subject matter experts
-I=informed, those who are kept up to date on progress

In your risk management plan what is the name of the document/form you use to
identify and classify the risks? - ANSWERrisk register

WBS (Work Breakdown Structure) - ANSWERlist of tasks to be completed

Información del documento

Subido en
4 de octubre de 2025
Número de páginas
6
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$12.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
shantelleG
4.1
(119)
Vendido
665
Seguidores
369
Artículos
18459
Última venta
2 días hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes