ENCE 325 Exam 2025
The widening of a state highway is an example of which sector of the construction
industry? - ANS-Infrastructure
Specialty trade contractors are typically hired on the job by which of the following? -
ANS-The contractor
A construction project is characterized by the following? - ANS-It results in deliverables,
it is unique, it uses resources (DUR)
In which of the following stages does the contractor have the major responsibility to
coordinate all necessary tasks associated with that stage? - ANS-Close-out
Which member of the contractor's team is responsible for the day-to-day production
activities on the jobsite? - ANS-The superintendent
The residential sector of the industry is characterized by which of the following? - ANS-
Projects are fairly low tech
What is the major rating system for green buildings - ANS-LEED
During the start-up and mobilization stage the following activities occur? - ANS-The
contractor moves onto the jobsite
The Owner is responsible for the project feasibility stage. - ANS-True
3 outcomes of the bidding and award stage - ANS-bid submittals by contractors, bid
package , award of construction contract
A design-build delivery method typically results in the owner having one contract with
the architect and another contract with the contractor. - ANS-False
The owner will decide which of the following as a result of the feasibility stage - ANS-
Move forward with project, abandon the project, adjust the scope, budget, and/or
schedule
Project design typically occurs in three distinct phases Schematic Design , Design
Development , and Construction Documents . Answer in the order of design phase
progression. - ANS-Schematic Design, Design Development , Construction Documents
ENCE 325
, ENCE 325
An owner is considering building a 120 unit housing development on the outskirts of
town. What would you refer to in determining if livestock would be allowed as part of the
property development? - ANS-Zoning Ordinance
Private owners may prefer to negotiate a fixed price with a contractor. In that situation,
the delivery method is called - ANS-Design Negotiate Build (DNB)
In an agency construction management (agency CM) delivery method, the CM is
financially responsible and self-performs work. - ANS-False
The primary technology enabler for the Integrated Project Delivery (IPD) method is -
ANS-Building Information Modeling (BIM) .
The primary advantages of the Design-Bid-Build delivery method include which of the
following (3) - ANS-Competitively Bid , Known upfront cost , Most familiar to all parties
For typical projects that are competitively bid, the process is fairly consistent and
includes five key steps. Which of the following is NOT one these steps. (4) - ANS-
Architect analyzes bids and awards contract; Architect completes bid package , Owner
solicits bids , Contractors review bid information , Contractors develop and submit bids
Integrity of the bidding process is important to the industry in protecting contractor's bid
submissions in a competitive environment. Trade secrets refers to maintaining the
confidentiality of Contractor's bid estimate. - ANS-True
There is a unique difference between open or closed projects during the bidding
process. For most publicly funded projects, open bidding (or allowing any qualified
contractor to bid) is the norm. - ANS-True
A "responsible" bidder is one who meets all the bidding requirements outlined in the bid
package. - ANS-False
Contractors consider many factors when deciding whether to bid on a job. These
include which of the following? Select all of the correct answers. (4) - ANS-Location of
the job, Time frame and liquidated damages, type of contract
The three primary types of surety bonds include which of the following. Select all of the
correct answers. - ANS-Bid bonds , performance bonds, payment bonds
An Owner estimate of project costs is the same as the Contractor estimate. - ANS-False
Which of the following are considerations when developing a project construction
estimate? (L, M, S, T) - ANS-Location of the Project, Market Conditions, Schedule and
Time Frame
Value Engineering is not the same as cost cutting. - ANS-True