D-Ring - ANS What is required on an OSHA approved harness for fall protection
6" or greater - ANS Openings _______ or greater at stairways, walkways, and open decks
must be guarded/covered
6' or above - ANS All window, door, and access openings _____ or above grade must be
guarded
2x4 or better - ANS Window and door guards must be ______
19.2" OC with 18" opening OR 24" OC with 2 rows of blocking & 3-1/2" toe kick - ANS For
clear story framing, stud bay spacing is not to exceed _______ OC with _____ opening OR
_______ OC with ____ rows of blocking and _____ toe kick
10ft or higher - ANS Working platforms have guardrails when _______ or higher
Planked - ANS Working platforms on scaffolds and decks are fully ______
At least 6", not more than 12" - ANS Scaffold planks are to be overlapped at least ___ but not
more than ___
Curb to curb - ANS ____ to ____ hard hat policy on all active construction sites
Eye protection - ANS ____________ must be worn when cutting, sawing, using nail guns,
mixing stucco or mortar, etc
N95 mask/respirator - ANS To be worn while cutting/ripping cement type siding, mixing stucco
or gypsum mortar or when working with any products that contains silica or other harmful
particles
3ft above roofline, 10ft tied off - ANS Ladders must extend ____ft above roof line and ladders
above ____ft must be tied off
Storm Water Pollution Prevention Plan - ANS What does SWPPP stand for?
True - ANS Containment is required under gasoline powered equipment
3000 PSI - ANS Minimum concrete PSI needed is...
, Concrete is placed in a continuous pour for monolithic slabs and walls - ANS True
1 gallon per cubic yard - ANS Water added on site is no more than ___ gallon(s) per cubic yard
90 minutes - ANS Concrete is discharged within ____ minutes after introduction of water to
cement
12 inches - ANS All exterior footings shall be placed at least ____ inches below the
undisturbed soil unless otherwise specified by EOR
1/4 thickness, 10ft intervals, 24 hours - ANS All non-post tensioned slabs have control joints
cut or tooled _____ thickness of the slab at _____ intervals within _____ hours of placement
2 or more - ANS Expansion joint in flatworm when the concrete slab is confined on ____ or
more sides
False - ANS Vegetative growth is allowed on pad area where concrete is poured
Sheathing or Wrapping - ANS Pipes passing through concrete are protected with _____ or
_____ that allows for movement including expansion and contraction of piping. Wall thickness
not less than 0.025 inch
Pipe Sleeve, 2 pipe sizes - ANS Pipes passing through a foundation wall shall be provided with
a _____ ______ that shall be built into the foundation wall. It shall be ____ pipe sizes greater
than the pipe passing through the wall
Backfilled & compacted - ANS All plumbing, electrical, and chases have been ______ and
_____ in accordance with soils report
Below the slab - ANS All conduits should be placed _____ the ______ as to not impact the
thickness of the slab
4" - ANS The slab depth is
2 rebar 24" OC - ANS What is placed diagonally over re-entrant corners
8" - ANS Overlap of wire mesh is 2 squares which is measured as ...
1/8" - ANS What is the gap size between all OSB sheathing?
16" OC - ANS Furring strip spacing at all tub and shower walls is...