Tamu Cosc 475 - Exam 1 Study Guide

Document preview thumbnail
Vista previa 2 fuera de 6 páginas

TAMU COSC 475 - EXAM 1 STUDY GUIDE

Vista previa del contenido

TAMU COSC 475 - EXAM 1 STUDY GUIDE

Five Branches of Critical Thinking - Answer -Problem Identification
Creative Thinking
Logical Analysis
Decision Making
Coordination

Problem Idnetification - Answer -Visualization
Fact Finding

Creative Thinking - Answer -Green Light Thinking
Brainstorming

Logical Analysis - Answer -Red Light Thinking
Reasoning

Decision Making - Answer -Gain Consensus
Decision Matrixes

Coordination - Answer -Plan Implementation
Control Stress

Notice to Proceed - Answer -implies that the site is free of encumbrances and the
contractor can occupy the site
The date of the NTP establishes the reference date from which the beginning of the
project is calculated

Fast Track - Answer -schedule method that starts activities at their ealiest possible time
to push subsequent activities up in their execution

Substantial Completion - Answer -the date is provided in the contract and represents
the earliest day that the owner can use the facility "for its intended purpose"
this date also specifies when liquidated damages will begin

Liquidated Damages - Answer -an assessment against the contractor for late
completion
intended to compensate the owner for lost revenue, the dates that control this are notice
to proceed and substantial completion

Stakeholders in Planning - Answer -Owners
Design Team
Builders
Agencies
Providers

, Reasons for project changes - Answer -People (different owners rep or superintendent)
Societal
Building Codes (every 3 years)
Environmental (Weather)
Unknown Conditions
Uncontrolled changes

Risk Scheduling - Answer -All high-risk items should be an activity in your schedule
Link high-risk activities to all affected activities
Delays lead to delays

4 Levels of WBS - Answer -Proposal
Pre-Construction
Construction
Look Ahead

Level 1: Proposal - Answer -goal is to summarize the overall project for client and
management
show start & finish dates for major project phases and milestone and include the project
time, goals, and objectives

Level 2: Preconstruction - Answer -contain more details for each summary phase
based on the level 1 schedule

Level 3: Construction - Answer -includes start and finish dates and links for all activities
critical path method is utilized
used as the project baseline for tracking progress
durations should not be longer than 10 days

Milestones - Answer -important items to watch that have zero durations (0 days)
May trigger the beginning or end of a phase
Ex: NTP, Dry-In, Substantial Completion, Top-Out, etc.

Information needed to determine a duration - Answer -Quantity of Work
Production Rate (Crew sizes, special productivity factor)
Hours per workday

Calculating Duration - Answer -Quantity of Work / Production Rate = Work Hours
Work Hours x Productivity Factor = Adjusted WH
Adj. Work Hours / Hours per workday = Activity Duration

Productivity Factor - Answer -production rates can be affected by multiple factors
EX: weather, congested space, layout, material handling, crew expertise, safety
requirements, complexity, etc.

Información del documento

Subido en
23 de septiembre de 2025
Número de páginas
6
Escrito en
2025/2026
Tipo
Otro
Personaje
Desconocido
$13.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
GEEKA
3.8
(376)
Vendido
2216
Seguidores
1450
Artículos
62635
Última venta
5 horas hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes