A project was authorized as an operational necessity to repair a design flaw in the date field on a
computer system that constrains the year number to two digits instead of permitting the year to be
indicated with four digits. During execution of the activity concerned with identifying the affected
software, five relevant software modules were discovered that had not been included in the scope
baseline. The project team must adjust the baselines to include the omitted scope.
Which change management phase does this scenario describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - (ANSWER)a) Preparing for the change
A general contractor is managing a highway construction project that will repair a flood-damaged road.
The Department of Transportation offered an incentive fee if the repairs are completed early. Therefore,
the project manager has established a rewards and recognition program and has communicated this
program to the project team member. The project's recognition program will reward project team
members who add value by accelerating the project while maintaining its ability to deliver the
completed scope correctly.
Which change management phase does this scenario describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - (ANSWER)c) Reinforcing the change
A general contractor is managing a construction project that will add a new conference room to an
existing office building. The project was documented in a fixed-price contract that specified a
completion date. The contract includes a damages clause imposing a late completion penalty if the
conference room is not ready for use by the due date. One month into the implementation, the
,WGU C722 Project Management Pre-assessment Actual Exam – Complete Questions and
Correct Verified Answers/ C722 Pre-assessment Test
customer wants to modify the room's lighting equipment. The requested change will delay the project's
critical path by three months.
Which process should be used to maintain the existing baseline?
a) Using a change management system to influence performance
b) Absorbing the change request in the baselines for time and cost
c) Focusing on the original scope
d) Using the risk management system to process change requests - (ANSWER)a) Using a change
management system to influence performance
A general contractor from Germany is managing a construction project in Norway that will add a new
conference room to an existing office building. The project needs to collect requirements from the client
prior to developing plans to build the new conference room.
Which two actions would prove useful to plan the project's quality?
a) Defining traceable and verifiable requirements that can be validated at project closure
b) Establishing metrics that describe what to measure and how to measure it
c) Using inventory to protect against defects during project implementation
d) Changing the work plan to account for the project experiencing common variation
e) Using slogans and numerical quotas to exhort resources to work harder - (ANSWER)a & b
a) Defining traceable and verifiable requirements that can be validated at project closure
b) Establishing metrics that describe what to measure and how to measure it
What is the name for the closing task where all project activities are reviewed to determine what went
right and what went wrong?
, WGU C722 Project Management Pre-assessment Actual Exam – Complete Questions and
Correct Verified Answers/ C722 Pre-assessment Test
a) Closeout review
b) Lessons learned review
c) Client deliverables review
d) Project manager review - (ANSWER)b) Lessons learned review
What is another name for lessons learned review that is often used by the military and other uniformed
services?
a) Rules of engagement
b) Activity report
c) Protocol assessment
d) After action report - (ANSWER)d) After action report
The customer of a project validates that scope has been completed for the second of three segments of
the project.
Which closure practice does this describe?
a) Iteration completion
b) Phase completion
c) Deliverable completion
d) Stage completion - (ANSWER)d) Stage completion
The customer of a project validates that the project scope has been completed, all invoices have been
paid, and the expected benefits have been realized.
Which closure practice does this describe?
Correct Verified Answers/ C722 Pre-assessment Test
A project was authorized as an operational necessity to repair a design flaw in the date field on a
computer system that constrains the year number to two digits instead of permitting the year to be
indicated with four digits. During execution of the activity concerned with identifying the affected
software, five relevant software modules were discovered that had not been included in the scope
baseline. The project team must adjust the baselines to include the omitted scope.
Which change management phase does this scenario describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - (ANSWER)a) Preparing for the change
A general contractor is managing a highway construction project that will repair a flood-damaged road.
The Department of Transportation offered an incentive fee if the repairs are completed early. Therefore,
the project manager has established a rewards and recognition program and has communicated this
program to the project team member. The project's recognition program will reward project team
members who add value by accelerating the project while maintaining its ability to deliver the
completed scope correctly.
Which change management phase does this scenario describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - (ANSWER)c) Reinforcing the change
A general contractor is managing a construction project that will add a new conference room to an
existing office building. The project was documented in a fixed-price contract that specified a
completion date. The contract includes a damages clause imposing a late completion penalty if the
conference room is not ready for use by the due date. One month into the implementation, the
,WGU C722 Project Management Pre-assessment Actual Exam – Complete Questions and
Correct Verified Answers/ C722 Pre-assessment Test
customer wants to modify the room's lighting equipment. The requested change will delay the project's
critical path by three months.
Which process should be used to maintain the existing baseline?
a) Using a change management system to influence performance
b) Absorbing the change request in the baselines for time and cost
c) Focusing on the original scope
d) Using the risk management system to process change requests - (ANSWER)a) Using a change
management system to influence performance
A general contractor from Germany is managing a construction project in Norway that will add a new
conference room to an existing office building. The project needs to collect requirements from the client
prior to developing plans to build the new conference room.
Which two actions would prove useful to plan the project's quality?
a) Defining traceable and verifiable requirements that can be validated at project closure
b) Establishing metrics that describe what to measure and how to measure it
c) Using inventory to protect against defects during project implementation
d) Changing the work plan to account for the project experiencing common variation
e) Using slogans and numerical quotas to exhort resources to work harder - (ANSWER)a & b
a) Defining traceable and verifiable requirements that can be validated at project closure
b) Establishing metrics that describe what to measure and how to measure it
What is the name for the closing task where all project activities are reviewed to determine what went
right and what went wrong?
, WGU C722 Project Management Pre-assessment Actual Exam – Complete Questions and
Correct Verified Answers/ C722 Pre-assessment Test
a) Closeout review
b) Lessons learned review
c) Client deliverables review
d) Project manager review - (ANSWER)b) Lessons learned review
What is another name for lessons learned review that is often used by the military and other uniformed
services?
a) Rules of engagement
b) Activity report
c) Protocol assessment
d) After action report - (ANSWER)d) After action report
The customer of a project validates that scope has been completed for the second of three segments of
the project.
Which closure practice does this describe?
a) Iteration completion
b) Phase completion
c) Deliverable completion
d) Stage completion - (ANSWER)d) Stage completion
The customer of a project validates that the project scope has been completed, all invoices have been
paid, and the expected benefits have been realized.
Which closure practice does this describe?