In which of the following locations pertaining to a wetland would a trench breaker need
to be installed during a pipeline construction project? - Answer-At the Wetland boundary
According to OSHA, lockout devices must meet which of the following criteria when
considering the prevention of removal from the device or box it is attached to except
for? - Answer-Be constructed and printed so that exposure to weather conditions or wet
and damp locations will cause the tag to deteriorate
Ensure that trench breakers are installed at which of the following locations? - Answer-
At the edge of wetlands
If the Inspector is observing the Survey Crews at the beginning of the job, which of the
following documents would the Inspector be expected to be familiar with? - Answer-
Access road drawings, Line List, Issued for Construction (IFC) Drawings
Inspectors are expected to function at all times as - Answer-Representatives of the
owner/operator
Markers installed above ground and developed during the design process include the
following except: - Answer-Stationing
Part of quality management focused on increasing the ability to fulfill quality
requirements - Answer-Quality inprovement
US Federal Regulations state that a pipeline installed in normal excavation may not be
located within 50 feet of any private dwelling, industrial building, or places of public
assembly unless _ _ _. - Answer-12" of cover is added 36" cover requirement
If you lock out/ tag out an intake line on a pump station, what energy are you preventing
from being released? - Answer-Hydraulic
During a pipeline construction project, any questions that may arise rewarding quality
and acceptability of work, materials furnished, should be decided upon by which of the
following? - Answer-Inspector, Inspection Team, and or Owner/Operator
During hydro-tests, the mitigation procedures regarding secondary containment and
refueling for any pumps installed within _ _ should be covered within the projects spill
prevention and response procedures - Answer-100'
, Who must be capable of managing, directing, and overseeing all pipeline construction
inspectors, as well as any specialized inspectors? - Answer-Chief Inspector
Per US federal regulations, a weld must be removed if it has a crack that is more than
what percent of the weld length? - Answer-8%
During a JSA, the foreman mentions frostbite as a potential hazard. What classification
of hazards would frostbite fall under? - Answer-Climatic hazards.
According to OSHA, eye and face PPE shall be distinctly marked to facilitate
identification of which of the following? - Answer-The manufacturer
When spark hazards exist, which of the following is recommended: - Answer-Pockets
be eliminated from the front of clothing.
Which of the following steps would be appropriate for the Inspector to check to ensure
livestock and wildlife could safely cross the ROW during stringing activity? - Answer-
Removal of a section of pipe.
Inspectors are expected to: - Answer-Establish professional relationships
According to OSHA, synthetic web slings shall be removed from service if any of the
following conditions are present, except: - Answer-Muddy/wet lifting legs
How long should a fire watch remain after welding or cutting operations are complete? -
Answer-Until the hazard of fire no longer exists
Cathodic protection should be installed _ _ _. - Answer-As soon as feasibly possible but
no longer than 1 year from installation
Removal and disposal of all brush, undergrowth, and timber. - Answer-Clearing
Which of the following should be marked "Red" on a pipeline project? - Answer-
Cathodic protection lines
Which of the following statements best describes the purpose for above ground
markers? - Answer-Used to identify underground facilities, not to circumvent the one call
process or locate for excavation.
During arc welding protective spectacles with lateral coverage, arc goggles, or other
approved protective eye wear shall: - Answer-be used in addition to welding helmets or
hand shields with filter and cover lenses.
with 100% Correct Answers
In which of the following locations pertaining to a wetland would a trench breaker need
to be installed during a pipeline construction project? - Answer-At the Wetland boundary
According to OSHA, lockout devices must meet which of the following criteria when
considering the prevention of removal from the device or box it is attached to except
for? - Answer-Be constructed and printed so that exposure to weather conditions or wet
and damp locations will cause the tag to deteriorate
Ensure that trench breakers are installed at which of the following locations? - Answer-
At the edge of wetlands
If the Inspector is observing the Survey Crews at the beginning of the job, which of the
following documents would the Inspector be expected to be familiar with? - Answer-
Access road drawings, Line List, Issued for Construction (IFC) Drawings
Inspectors are expected to function at all times as - Answer-Representatives of the
owner/operator
Markers installed above ground and developed during the design process include the
following except: - Answer-Stationing
Part of quality management focused on increasing the ability to fulfill quality
requirements - Answer-Quality inprovement
US Federal Regulations state that a pipeline installed in normal excavation may not be
located within 50 feet of any private dwelling, industrial building, or places of public
assembly unless _ _ _. - Answer-12" of cover is added 36" cover requirement
If you lock out/ tag out an intake line on a pump station, what energy are you preventing
from being released? - Answer-Hydraulic
During a pipeline construction project, any questions that may arise rewarding quality
and acceptability of work, materials furnished, should be decided upon by which of the
following? - Answer-Inspector, Inspection Team, and or Owner/Operator
During hydro-tests, the mitigation procedures regarding secondary containment and
refueling for any pumps installed within _ _ should be covered within the projects spill
prevention and response procedures - Answer-100'
, Who must be capable of managing, directing, and overseeing all pipeline construction
inspectors, as well as any specialized inspectors? - Answer-Chief Inspector
Per US federal regulations, a weld must be removed if it has a crack that is more than
what percent of the weld length? - Answer-8%
During a JSA, the foreman mentions frostbite as a potential hazard. What classification
of hazards would frostbite fall under? - Answer-Climatic hazards.
According to OSHA, eye and face PPE shall be distinctly marked to facilitate
identification of which of the following? - Answer-The manufacturer
When spark hazards exist, which of the following is recommended: - Answer-Pockets
be eliminated from the front of clothing.
Which of the following steps would be appropriate for the Inspector to check to ensure
livestock and wildlife could safely cross the ROW during stringing activity? - Answer-
Removal of a section of pipe.
Inspectors are expected to: - Answer-Establish professional relationships
According to OSHA, synthetic web slings shall be removed from service if any of the
following conditions are present, except: - Answer-Muddy/wet lifting legs
How long should a fire watch remain after welding or cutting operations are complete? -
Answer-Until the hazard of fire no longer exists
Cathodic protection should be installed _ _ _. - Answer-As soon as feasibly possible but
no longer than 1 year from installation
Removal and disposal of all brush, undergrowth, and timber. - Answer-Clearing
Which of the following should be marked "Red" on a pipeline project? - Answer-
Cathodic protection lines
Which of the following statements best describes the purpose for above ground
markers? - Answer-Used to identify underground facilities, not to circumvent the one call
process or locate for excavation.
During arc welding protective spectacles with lateral coverage, arc goggles, or other
approved protective eye wear shall: - Answer-be used in addition to welding helmets or
hand shields with filter and cover lenses.