Examen

WGU C722 Project Management OA Exam 2025/2026 – Actual Questions with Verified Correct Answers & Expert Solutions

Document preview thumbnail
Vista previa 3 fuera de 22 páginas

WGU C722 Project Management OA Exam 2025/2026 – Actual Questions with Verified Correct Answers & Expert Solutions

Vista previa del contenido

WGU C722 Project Management OA
Exam 2025/2026 – Actual Questions with
Verified Correct Answers & Expert
Solutions

Question 1

What is the primary role of a project manager in the PMI framework?
A. To execute technical tasks
B. To facilitate communication and manage stakeholders
C. To develop the project budget
D. To approve all project deliverables

Answer: B
Rationale: The project manager’s primary role is to facilitate communication, coordinate team
efforts, and manage stakeholders to ensure project success, aligning with the PMI People
domain.



Question 2

Which process group initiates a project?
A. Planning
B. Executing
C. Initiating
D. Closing

Answer: C
Rationale: The Initiating process group involves defining the project and obtaining
authorization, setting the foundation for all subsequent project activities (PMI Process domain).



Question 3

A stakeholder requests a change to the project scope. What is the first step the project manager
should take?
A. Implement the change immediately

,B. Evaluate the impact on the project
C. Update the project schedule
D. Reject the change request

Answer: B
Rationale: Evaluating the impact of a change request ensures informed decision-making,
considering scope, schedule, cost, and risks (PMI Process domain).



Question 4

Which tool is used to identify project risks?
A. Gantt chart
B. Risk register
C. Work breakdown structure (WBS)
D. Critical path method (CPM)

Answer: B
Rationale: The risk register is a tool used to identify, document, and manage project risks,
aligning with risk management processes (PMI Process domain).



Question 5

A project team member is underperforming. What is the project manager’s best action?
A. Replace the team member
B. Address the issue through coaching
C. Ignore the performance issue
D. Escalate to senior management

Answer: B
Rationale: Coaching supports team development and addresses performance issues
constructively, aligning with leadership skills in the PMI People domain.



Question 6

What is the purpose of a project charter?
A. To detail the project schedule
B. To authorize the project and define objectives
C. To assign project resources
D. To monitor project progress

, Answer: B
Rationale: The project charter formally authorizes the project, outlines objectives, and identifies
the project manager, initiating the project (PMI Process domain).



Question 7

Which cost estimation technique uses historical data from similar projects?
A. Bottom-up estimation
B. Parametric estimation
C. Analogous estimation
D. Three-point estimation

Answer: C
Rationale: Analogous estimation uses historical data from similar projects to estimate costs or
duration, suitable for early project phases (PMI Process domain).



Question 8

A project is behind schedule. Which technique helps identify tasks with no slack time?
A. Earned value analysis
B. Critical path method
C. SWOT analysis
D. Stakeholder analysis

Answer: B
Rationale: The critical path method identifies tasks with zero slack, critical to the project
schedule, helping prioritize efforts (PMI Process domain).



Question 9

Which conflict resolution technique promotes a win-win solution?
A. Forcing
B. Smoothing
C. Collaborating
D. Avoiding

Answer: C
Rationale: Collaborating seeks mutually beneficial solutions by addressing all parties’ concerns,
fostering teamwork (PMI People domain).

Información del documento

Subido en
18 de septiembre de 2025
Número de páginas
22
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$16.50

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TutorRicks
3.6
(51)
Vendido
365
Seguidores
51
Artículos
2903
Última venta
11 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes