Phase I equipment is related all of the following except? -
Answer-Dispenser mounted vapor recovery equipment
According to EO VR-201-A, the only authorized hose
configuration is? - Answer-Lazy J- EO VR-201
The most ARB approved Phase II vapor recovery is? -
Answer-EVR
When a certified Healy Technician is replacing the VP 100
during operational hours, he should eliminate potential
problems by, except? - Answer-review service with gas
station operator
The following component is not part of the Healy Phase II
vapor recovery system? - Answer-Healy Model 900 Vapor
motor
, 2|Page
The max dispensing floe rate of a Healy 900 series EVR
nozzle is ? - Answer-10 GPM
According to VR-201-A, a __________________ should
be installed on the Healy system if the flow rate us above
10 GMP? - Answer-Flow limiter
The quarterly inspection and Testing of a Healy Phase II
EVR system should include the following except? -
Answer-Conduct a pressure decay test by a Healy
Certified Technician - EO VR_-201-A
The first sign of oxygen depletion is? - Answer-
Accelerated breathing and heartbeat
According to the PEI 500, a method of removing a portion
of a facility from service are, except? - Answer-Noting in
defective equipment log
What procedure checks the integrity of the vapor check
valve in the nozzle? - Answer-Nozzle bag test
ICC Vapor Recovery Exams Actual Exam 2025/2026
Complete Questions And Correct Detailed Answers
(Verified Answers) |Already Graded A+||Newest
Version!!!
Phase I equipment is related all of the following except? -
Answer-Dispenser mounted vapor recovery equipment
According to EO VR-201-A, the only authorized hose
configuration is? - Answer-Lazy J- EO VR-201
The most ARB approved Phase II vapor recovery is? -
Answer-EVR
When a certified Healy Technician is replacing the VP 100
during operational hours, he should eliminate potential
problems by, except? - Answer-review service with gas
station operator
The following component is not part of the Healy Phase II
vapor recovery system? - Answer-Healy Model 900 Vapor
motor
, 2|Page
The max dispensing floe rate of a Healy 900 series EVR
nozzle is ? - Answer-10 GPM
According to VR-201-A, a __________________ should
be installed on the Healy system if the flow rate us above
10 GMP? - Answer-Flow limiter
The quarterly inspection and Testing of a Healy Phase II
EVR system should include the following except? -
Answer-Conduct a pressure decay test by a Healy
Certified Technician - EO VR_-201-A
The first sign of oxygen depletion is? - Answer-
Accelerated breathing and heartbeat
According to the PEI 500, a method of removing a portion
of a facility from service are, except? - Answer-Noting in
defective equipment log
What procedure checks the integrity of the vapor check
valve in the nozzle? - Answer-Nozzle bag test