__________ is the planning, organizing, monitoring, controlling and
reporting of all aspects of a project. - CORRECT ANSWER - project
management
__________ is the property in which a pipeline company and a
landowner both have a ___________
interest. - CORRECT ANSWER - right of way (ROW), legal
__________ is the specified way to carry out an activity or a process. -
CORRECT ANSWER - procedure
___________ is the plan devised between the Owner and Crossing Party
to specify the details and
provisions under which the crossing construction shall occur. -
CORRECT ANSWER - crossing plan
_________________ as used in ASME B31.8 is the portion of the route of
a pipeline or main that lies
within, runs in a generally parallel direction to, and does not necessarily
cross the rights-of-way of a
road, street, highway, or railroad. - CORRECT ANSWER - parallel
encroachment
,"Wetland" includes any area that is not in actively cultivated or rotated
cropland and that satisfies the
requirements of the current federal methodology for identifying and
delineating wetlands - CORRECT ANSWER - true
A _____________ is a is a written document, associated with all
remedial site sampling activities, which
presents in specific terms the organization objectives, functional
activities, and specific quality
assurance (QA) and quality control (QC) activities designed to achieve
the data quality objectives of a
specific project(s) or continuing operation(s). - CORRECT ANSWER -
quality assurance project plan
A _____________ is a pressure-containing component used for repeated
access to the interior of a
piping system. - CORRECT ANSWER - quick opening closure
A "Waterbody" includes any natural or artificial stream, river, or
drainage with perceptible flow at the
time of crossing, and other permanent waterbodies such as ponds and
lakes. Which of the following
statements is incorrect? - CORRECT ANSWER - "minor waterbody"
includes all waterbodies less than or equal to 12 feet wide at the water's
, edge at the time of crossing;
A covered task is identified by the operator as a task that: - CORRECT
ANSWER - Is performed on a pipeline facility
Is an operations or maintenance task
Is performed as a requirement of 49 CFR 192.801
Affects the operation or integrity of the pipeline
A line marker must be placed and maintained as close as practical over
each buried main and
transmission; at each crossing of a public road & railroad, and wherever
necessary to identify the
location of the transmission line or main to reduce the possibility of
damage or interference - CORRECT ANSWER - true
A release, which generally means any spilling, leaking, pumping, pouring,
emitting, emptying,
discharging, injecting, escaping, leaching, dumping, or disposing into the
environment (including the
abandonment or discarding of barrels, containers, and other closed
receptacles containing any
hazardous substance or pollutant or contaminant), may be discovered
through: - CORRECT ANSWER - Notification of a release by a federal
or state permit holder when required by its permit;