• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 4 fuera de 46 páginas
Examen

VA DEQ ESC INSPECTOR EXAM 2025 UPDATED ACTUAL EXAM WITH CORRECT SOLUTIONS.

Document preview thumbnail
Vista previa 4 fuera de 46 páginas

VA DEQ ESC INSPECTOR EXAM 2025 UPDATED ACTUAL EXAM WITH CORRECT SOLUTIONS.

Vista previa del contenido

1 | Page

VA DEQ ESC INSPECTOR EXAM 2025
UPDATED ACTUAL EXAM WITH
CORRECT SOLUTIONS.

VESCP - correct answer- Virginia Erosion and Sediment
Control Program


- Administered by counties/cities (must), towns (may)
- MUST BE APPROVED




Minimum Standard 1 - correct answer- Stabilization


permanent or temporary soil stabilization shall be applied to
denuded areas within seven days after final grade is reached
on any portion of the site; temporary soil stabilization shall be
applied within seven days to denuded areas that may not be at
final grade but will remain dormant for longer than 14 days;
permanent stabilization shall be applied to areas that are to be
left dormant for more than one year




Site NOT at Final Grade - correct answer- - stabilize in 14 days
- temporarily seed
- mulch
- permanently stabilize if dormant > 1 year

,2 | Page




Site at Final Grade - correct answer- - stabilize in 7 days
(recommended immediately)
- permanently or temporarily seed and mulch
- mulch/matting/straw




Minimum Standard 2 - correct answer- Stock Piles, Waste and
Borrow Areas


during construction, soil stock piles and borrow areas shall be
stabilized or protected with sediment trapping measures


mulch prevents erosion by protecting the surface from raindrop
impact and silt fence intercepts and detains from disturbed
areas




Minimum Standard 3 - correct answer- Permanent Vegetation


permanent vegetation cover shall be established on denuded
areas not otherwise permanently stabilized (permanent
vegetation shall not be considered established until a ground
cover is achieved that is uniform, mature enough to survive,
and will inhibit erosion *there is no % associated with this*)

,3 | Page

reduce erosion and decrease sediment yield from disturbed
area


this is the standard used to verify that a site is ready for release
of bonds or surety




Minimum Standard 4 - correct answer- First-Step Measures


Sediment basins and traps, perimeter dikes, sediment barriers
and other measures intended to trap sediment shall be
constructed as a first step in any land-disturbing activity and
shall be made functional before upslope land disturbance takes
place


a certain amount of initial land disturbance may be required to
provide access for equipment to install the perimeter controls,
but site clearing and grading should be kept to a minimum until
the perimeter controls are in place


intercepts and detains small amounts of sediment from
disturbed areas during construction operation to prevent
sediment from leaving the site and decrease velocity of sheet
flows and low-to-moderate level channel flow




Perimeter Controls - correct answer- assures that sediment
does not leave the perimeter of the land-disturbing area once
site clearing, grading, and construction commences

, 4 | Page



Examples: silt fences, sediment traps, sediment basins,
construction entrance, temporary diversions, diversions




Minimum Standard 5 - correct answer- Earthen Structure
Stabilization


stabilization measures shall be applied to earthen structures
such as dams, dikes, and diversions immediately after
installation


reduce erosion and sedimentation and reduce damage from
sediment and runoff to downstream or off-site areas




Minimum Standard 6 - correct answer- Traps and Basins


sediment traps and basins shall be designed and constructed
based upon the total drainage area (not just disturbed area) to
be served by the trap or basin




Sediment Traps - correct answer- minimum storage capacity
shall be 134 cubic yards per acre of drainage area and shall
only control drainage areas less than 3 acres

Información del documento

Subido en
3 de septiembre de 2025
Número de páginas
46
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$15.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
ScholaryNurse
4.1
(11)
Vendido
76
Seguidores
0
Artículos
4805
Última venta
1 semana hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes