Where is the requirement for construction of sewage pumpout
facilities specified - ANSWER-Water quality certification for the for
of engineers section 10 permit
Each marina will prominently display signs stating what -
ANSWER-It is illegal to discharge untreated sanitary waste into
US waters and direct boaters to the pumpout facilities
Pipe and joints in stream crossing will be tested where -
ANSWER-In place
What must stream crossing pipe and joints do to pass the test -
ANSWER-- zero infiltration - protected from hydraulic m,
longitudinal, vertical, horizontal loads, erosion, and impact
,2|Page
When can sewers be laid on piers across rivers ir streams -
ANSWER-When it can be demonstrated that there are no other
practical alternatives
How will sewers on piers be constructed compared to sewers
entering or crossing streams - ANSWER-The same
How many days prior to the the desired inspection date should
you make your appointment - ANSWER-2 working days
What must happen before covering all or any of the sewage
disposal system - ANSWER-Must be inspected and approved
What has to happen with roof and surface water - ANSWER-Must
be directed away or downslope from sewage disposal system by
footing or foundation floor drains or surface diversion ditches
What must be done to all pipe joints including those in the drain
field - ANSWER-Glued and watertight
, 3|Page
How much fall should there be on all parts of the building sewer -
ANSWER-1/8 inch per foot
Elbows or bends should be no greater than ____ - ANSWER-45
degrees, 90 degree sweeps may be used
What is the rating needed for solid pipe under driving,parking, or
any vehicle encroaching areas - ANSWER-ASTM- 3034 crush
rating, or enclosed in a pipe that does meet it
Who is the doe - ANSWER-Department of ecology
What department criteria do you follow for sewage that crosses
over waterline - ANSWER-Department of Ecology (DOE)
All On-site septic systems should be watertight except for the
______ - ANSWER-Dispersal component
SEPTIC LICENSE EXAM (VERSION 2) LATEST 2025/2026 ACTUAL
EXAM WITH COMPLETE QUESTIONS AND CORRECT DETAILED
ANSWERS (100% VERIFIED ANSWERS) |ALREADY GRADED A+|
||PROFESSOR VERIFIED|| ||BRANDNEW!!!||
Where is the requirement for construction of sewage pumpout
facilities specified - ANSWER-Water quality certification for the for
of engineers section 10 permit
Each marina will prominently display signs stating what -
ANSWER-It is illegal to discharge untreated sanitary waste into
US waters and direct boaters to the pumpout facilities
Pipe and joints in stream crossing will be tested where -
ANSWER-In place
What must stream crossing pipe and joints do to pass the test -
ANSWER-- zero infiltration - protected from hydraulic m,
longitudinal, vertical, horizontal loads, erosion, and impact
,2|Page
When can sewers be laid on piers across rivers ir streams -
ANSWER-When it can be demonstrated that there are no other
practical alternatives
How will sewers on piers be constructed compared to sewers
entering or crossing streams - ANSWER-The same
How many days prior to the the desired inspection date should
you make your appointment - ANSWER-2 working days
What must happen before covering all or any of the sewage
disposal system - ANSWER-Must be inspected and approved
What has to happen with roof and surface water - ANSWER-Must
be directed away or downslope from sewage disposal system by
footing or foundation floor drains or surface diversion ditches
What must be done to all pipe joints including those in the drain
field - ANSWER-Glued and watertight
, 3|Page
How much fall should there be on all parts of the building sewer -
ANSWER-1/8 inch per foot
Elbows or bends should be no greater than ____ - ANSWER-45
degrees, 90 degree sweeps may be used
What is the rating needed for solid pipe under driving,parking, or
any vehicle encroaching areas - ANSWER-ASTM- 3034 crush
rating, or enclosed in a pipe that does meet it
Who is the doe - ANSWER-Department of ecology
What department criteria do you follow for sewage that crosses
over waterline - ANSWER-Department of Ecology (DOE)
All On-site septic systems should be watertight except for the
______ - ANSWER-Dispersal component