COSC 354 Project Management Exam #3 Questions and Answers Already Passed Latest Update Steps involved in the planning and scheduling process - Answers - Establish Project Objective(s) - Typically owner driven - Identify Project Tasks/Activities (definable work activities) - Determine Task/Activity Sequence (what activity must proceed and what activity must succeed?) - Determine Task/Activity Durations (the estimate can be very helpful here) - Perform Schedule calculations (if using CPM) to determine the project's Critical Path - Revise and Adjust the Schedule (Could the duration be shortened to take advantage of a bonus for finishing early?) - Monitor and Control against the baseline or target schedule (the goal is to stay on target and finish the project on time!) Scheduling throughout the project (preconstruction, construction, and postconstruction) - Answers Preconstruction Phase: - Planning and scheduling is a key activity during this phase - Project financing, commitments to the owner, and market projections all depend upon the scheduled start and completion date - The initial schedule should be viewed as an opportunity to build the project on paper and help the project team to begin making intelligent management decisions - As the project evolves, the team will continually refine the schedule to optimize the project activity durations Construction Phase: - Schedules are essential to the successful coordination of a project's day-to-day operations (material, equipment, and labor) - As a project progresses, delays will occur! Anticipate delays and be ready to effectively deal with them. - Job progress is closely tracked, and the schedule is often placed on the wall of the job office/trailer where it is clearly visible to everyone (which Lean Builder tool is this?) Postconstruction Phase: - In this final phase, the schedule can be used to coordinate and control when the owner begins to occupy the facility - Most projects require testing and acceptance of equipment and systems (remember commissioning?) and training of end users. The schedule can be helpful in this regard as well! - Lastly, postconstruction scheduling can be part of an effective recordkeeping program for "after action" reviews so that better planning and scheduling can occur on future projects The types of schedules and the pros/cons of each - Answers Bar Charts: Graphically Represents: - Planned overall length of project - Planned duration of each major project component

Vista previa del contenido

COSC 354 Project Management Exam #3 Questions and Answers Already Passed Latest
Update 2025-2026

Steps involved in the planning and scheduling process - Answers - Establish Project Objective(s)
- Typically owner driven

- Identify Project Tasks/Activities (definable work activities)

- Determine Task/Activity Sequence (what activity must proceed and what activity must
succeed?)

- Determine Task/Activity Durations (the estimate can be very helpful here)

- Perform Schedule calculations (if using CPM) to determine the project's Critical Path

- Revise and Adjust the Schedule (Could the duration be shortened to take advantage of a bonus
for finishing early?)

- Monitor and Control against the baseline or target schedule (the goal is to stay on target and
finish the project on time!)

Scheduling throughout the project (preconstruction, construction, and postconstruction) -
Answers Preconstruction Phase:

- Planning and scheduling is a key activity during this phase

- Project financing, commitments to the owner, and market projections all depend upon the
scheduled start and completion date

- The initial schedule should be viewed as an opportunity to build the project on paper and help
the project team to begin making intelligent management decisions

- As the project evolves, the team will continually refine the schedule to optimize the project
activity durations



Construction Phase:

- Schedules are essential to the successful coordination of a project's day-to-day operations
(material, equipment, and labor)

- As a project progresses, delays will occur! Anticipate delays and be ready to effectively deal
with them.

- Job progress is closely tracked, and the schedule is often placed on the wall of the job
office/trailer where it is clearly visible to everyone (which Lean Builder tool is this?)

, Postconstruction Phase:

- In this final phase, the schedule can be used to coordinate and control when the owner begins
to occupy the facility

- Most projects require testing and acceptance of equipment and systems (remember
commissioning?) and training of end users. The schedule can be helpful in this regard as well!

- Lastly, postconstruction scheduling can be part of an effective recordkeeping program for
"after action" reviews so that better planning and scheduling can occur on future projects

The types of schedules and the pros/cons of each - Answers Bar Charts: Graphically Represents:

- Planned overall length of project

- Planned duration of each major project component

- Calendar start and finish dates for each project phase Advantages

- Simple and quick to produce

- Simple to read/comprehend

- Good for executive review and public meetings Disadvantages

- Does not communicate the interrelationships among project activities



Matrix Schedule:

- Typically used for repetitive work, such as multi-story buildings

- A good tool for communicating/controlling field activities because it can be posted in the job
office and updated as work progresses

Advantages

- Easily understood by nontechnical people

- Best when used as a coordination tool in the field

Disadvantages

- Lacks detail

- does not typically consider all project activities

Información del documento

Subido en
20 de agosto de 2025
Número de páginas
12
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$10.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TutorJosh
3.5
(76)
Vendido
493
Seguidores
16
Artículos
32839
Última venta
3 horas hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes