• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 3 fuera de 18 páginas
Examen

Project Management Accurate Real Exam Frequently Tested Question Verified Correct

Document preview thumbnail
Vista previa 3 fuera de 18 páginas

Program - Answer A program is a group of related projects designed to accomplish a common goal over an extended period of time. Project - Answer A project is a temporary endeavor undertaken to create a unique product, service, or result. Project life cycle - Answer The stages found in all projects— definition, planning, execution, and delivery. Project Management Professional (PMP) - Answer An individual who has met specific education and experience requirements set forth by the Project Management Institute, has agreed to adhere to a code of professional conduct, and has passed an examination designed to objectively assess and measure project management knowledge. In addition, a PMP must satisfy continuing certification requirements or lose the certification.

Vista previa del contenido

PMI project management Real Exam
Questions and Answers 100% Pass
considering that stress points are measured in hours, how many points will a team be able to score in
the next iteration if its dedication factor is 60 percent and it has 300 hours for the next iteration. -
Answer 180



Which; leadership style consist of focusing on concrete objectives to reward your team? - Answer
Transactional



Which three statements are objectives of business analysis? - Answer 1. manage risks and reduce work.

2.manage stake holder satisfaction.

3.manage defects in delivered products.



which meeting is held after the planning stage is finished and the project execution begins? - Answer
kick off meeting



which of the following project activities, which start at the same time, are critical activities? - Answer
programming the websites operation and links, with a duration of five weeks.



Which of the following documents provides a project manager with his or her authority? - Answer The
project charter



what type of power is indispensable for a project manger - Answer formal



you are working on a project. The program manager contacts you to communicate that due to a change
of conditions in the program, the objectives of your project will need to be revised. In this situation,
which two statements are true? - Answer 1.A program is a group of related projects.



2.The program manager can influence the project.

,When estimating the duration of an activity during project scheduling, what technique can be used to
compare a projects activities with similar ones form a previous project. - Answer analogous estimation



If the change affects the project baseline - Answer change control board



if the change affects the company's objectives with respect to the project - Answer sponsor



If the change does not affect the baselines or the company's objects but does affect the project's
contingency reserves. - Answer project manager



If there are changes to the management of or approach to the work that do not affect the project
baselines. - Answer project team



In a predictive project, which knowledge area should be well defined before you define the other three?
- Answer Scope



Which of the following types of requirements is compiled by the project manager? - Answer Project
quality requirements



When should a project business case be developed - Answer before the start of the project



Which three areas are critical in business analysis and should be known to the business analyst? -
Answer 1.culture

2.people

3.processes



In which scenario is it advisable to use questionnaire and survey tools? - Answer with many non-key
stakeholders whose opinion maybe important.



In an agile project, what three elements should be indicated in the teams task during an iteration? -
Answer 1.person in charge

2.effort

, 3.description of the task



what communication method includes an intranet where you upload documentation? - Answer pull
command



In an agile project using work cycles, in what order should the following meetings be held? - Answer
Planning meeting

daily standup

review meeting

retrospective meeting



During the execution of a project, a change in the market means the final deadline has to be moved
forward by a month. Because this project has serious technological implications for the company, any
risk that may occur will have a highly negative impact. In this situation, how can you speed up the
delivery of the project? - Answer crash the schedule



which of the following is not part of the communications management plan? - Answer work packages



Which three statements belong to the 12 principles of the agile manifesto? - Answer 1.Customer
satisfaction by rapid delivery of useful software.



2.continuous attention to technical excellence and good design.



3.Working software is the principle measure of progress.



Which statement about the product backlog and iteration backlog is correct? - Answer The product
backlog contains the stories and the iteration backlog contains the task.



In a contract with incentives, a provider will get a bonus or receive a penalty depending on the results of
their services. What is the main benefit of this type of contract? - Answer involving the provider in the
project

Información del documento

Subido en
15 de agosto de 2025
Número de páginas
18
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$12.39

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Topscore101
5.0
(1)
Vendido
7
Seguidores
0
Artículos
1880
Última venta
9 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes