A postaward orientation aids both Government and contractor personnel to: - Answer -
Achieve a clear and mutual understanding of all contract requirements and identify and
resolve potential problems
FAR 42.501
When late in paying an otherwise acceptable invoice, the Government will: - Answer -
Pay an interest penalty
FAR 32.907(a)
When acquiring commercial items, quality assurance is primarily the responsibility of: -
Answer -The contractor
FAR 46.202-1
You have a requirement for an online subscription to Engineering News Record. The
site owner requires payment before they will provide the license code number to
activate the annual subscription. Which payment form is required? - Answer -An
advance payment
FAR 32.102(a)
What agency does DoD typically delegate contract administrative functions for supply
contracts? - Answer -Defense Contract Management Agency
FAR 42.201(b)
A purpose of a postaward orientation is to: - Answer -Achieve a clear and mutual
understanding of all contract requirements
42.501(a)
A contractor employee accidentally broke a test fixture that belongs to the Government
and is accountable to a Government contract. Generally speaking: - Answer -
Contractors are not held liable for loss of Government property
FAR 45.104
According to the FAR, the acquisition team: - Answer -Includes the contractor
FAR 1.102-3
, With limited exceptions, a Contractor Performance Assessment Reporting System
(CPARS) report is required: - Answer -When the contract dollar value exceeds the
simplified acquisition threshold
FAR 42.1502(b)
To be determined responsible by a contracting officer, a prospective contractor must: -
Answer -Have adequate financial resources to perform the contract, or the ability to
obtain them
FAR 9.104-1(a)
In ensuring overall quality of items and services received under a contract, which of the
following is the responsibility of the Government? - Answer -Quality assurance
surveillance
FAR subpart 46.1
The Government's preferred remedy to nonconforming goods or services is: - Answer -
Allow the contractor to repair or replace the nonconforming items, as long as there is
still time left within the required delivery schedule
FAR 46.407
Quality assurance policies and procedures found in FAR part 46: - Answer -Apply to
both the Government and contractor
FAR 46
Contractors are responsible for: - Answer -Tendering to the Government for
acceptance only those supplies or services that conform to contract quality
requirements
FAR 46.105
Does the Government have the right to inspect a product before it is accepted? -
Answer -Yes, always
FAR 52.246-2
When does title for a completed product transfer to the Government, assuming the
product meets all contract requirements? - Answer -Upon formal acceptance by the
Government
FAR 46.505(a)