Examen

CCIFP Practice Exam – Questions With Expert Solutions

Document preview thumbnail
Vista previa 4 fuera de 34 páginas

CCIFP Practice Exam – Questions With Expert Solutions

Vista previa del contenido

CCIFP Practice Exam – Questions With Expert Solutions

A contractor has a claim for extended field overhead on a federal government
contract. the contract billings were $10 million. the contractor's total billings
during the contract period were $100 million. the contractors total overhead
cost during the contract period were $3 million. the contractor worked 1 year
on the project. the government caused the contractor to be delayed by 60 days
on this contract. using the Eichleay formula, what is the contractors claim for
overhead due to the delay?

- $42,353
- $49,315
- $493,151
- $59,016 Correct Answer - $49,315

Contract billings / Total billings during contract period = Overhead %
$10,000,000 / $100,000,000 = 10%

Overhead % x Total overhead during contract period = Allocated overhead
10% x $3,000,000 = $300,000

Allocated overhead / Days of contract performance = Overhead per day
$300, = $821.92

Overhead per day x Number of days delayed = Overhead due to delay
$821.92 x 60 = $49,315

On a typical construction project whereby the owner has requested
performance and payment bonds from the general contractor, the owner is
referred to as the...

- Principal
- Obligee
- Underwriter
- Obligor Correct Answer - obligee

when computing the taxable income for a proposed capital project, the
financial manager should use which tax rate?

,- Average
- Base
- Marginal
- Capital Gains Correct Answer - marginal

What coverage trigger is used with a commercial general liability policy when
the insurance policy in effect at the time the property damage loss occurs
responds to that loss, regardless of when the contractor learns about the loss
or when a claim is filed against the contractor?

- Limitation of liability trigger
- Stop loss trigger
- Occurrence trigger
- Claims made trigger Correct Answer - Occurrence trigger


Under an occurrence-based policy, coverage is triggered by the date the
damage or injury occurs, not when the claim is made or discovered. This
means the policy in force at the time of the incident will respond, even if the
claim is filed years later.

Claims made trigger applies when the policy only covers claims made during
the policy period, regardless of when the incident occurred. This is common in
professional liability insurance but not typical for standard CGL policies.

Pursuant to GAAP, which of the following methods of recognizing revenue is
most frequently used in construction accounting?

- Accrual (Billing) Method
- Cash Method
- Completed Contract Method
- Percentage of Completion Method Correct Answer - Percentage of
Completion Method

Contractors can maximize controls over cash disbursements by implementing
some of the following..... 15.06 [2] Correct Answer - 1) Knowing vendor
systems
2) Using Controlled Disbursement bank Accounts
3) Implementing an open purchase order/contract commitment system

,4) Soliciting Cooperation from Project Management to minimize early
Payments to subcontractors and suppliers

What role do Domain Controllers Serve within an Active Directory? Correct
Answer - To manage trust among the domains by granting access to users
from one domain to the other via a proper security authentication process.

a construction company should record interest rate swaps purchased for
business purposes using which method of valuation?

- Intrinsic value
- Fair market value
- Net present value
- Discounted value Correct Answer - Fair Market Value

Which of the following contract provisions is exculpatory?

- Provision for Arbitration
- No damages for delay clause
- Performance specifications
- Compensation for extra work Correct Answer - No damages for delay
clause

An exculpatory clause is a contract provision that relieves one party from
liability for certain damages or losses. The "no damages for delay" clause does
exactly that—it limits or eliminates the contractor's ability to recover
damages (like extended overhead or lost profits) due to delays, even if those
delays are caused by the owner. This clause shifts the risk of delay-related
costs from the owner to the contractor, effectively excusing the owner from
financial responsibility for certain types of delays.

Exculpatory sounds like excuse

Section 460 of the Internal Revenue Code defines the following? 29.03 [b]
Correct Answer - 29.03 [b]

ABC Company hires a subcontractor to work on a project that will span over 5
years. The subcontract amount is $500,000 and is to be billed monthly to ABC

, Company. Retention of 10% is to be held until the subcontractor is 75%
complete and the owner of the project has approved the release of retention.

How should ABC Company record the subcontractor retention on its records
in the first year of the project?

- Non-current liability
- Current liability
- Contract billing
- Current asset Correct Answer - current-liability

under the completed contract method of accounting, how are general and
administrative cost realized on the income statement? Correct Answer -
Expensed and recognized in the year incurred.

The length of a contractors operation cycle determines what is considered a
current asset or liability for their classified balance sheet. it has become
common practice in the construction industry to classify all contract-related
assets and liabilities as current based on what measurement?

- 24 months
- Always 12 months
- Average length of their contracts
- 18 months Correct Answer - average length of their contract.

five steps of strategic planning are: develop an internal understanding of
existing businesses, identify new business opportunities, ______________, develop
a strategic plan, implement the plan. Correct Answer - analyze
alternatives

a loss or claim under a surety bond is generally triggered by....

- Property damage
- Losses that are expressly insured by the policy
- A default of the contract
- Personal injury Correct Answer - a default of the contract

Property damage: This is typically covered by insurance, not a surety bond.

Información del documento

Subido en
31 de julio de 2025
Número de páginas
34
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$25.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
StudyHall
3.8
(231)
Vendido
1358
Seguidores
825
Artículos
17365
Última venta
4 días hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes