Examen

RTPM Study guide based on actual test with correct answers

Document preview thumbnail
Vista previa 4 fuera de 85 páginas

RTPM Study guide based on actual test with correct answers

Vista previa del contenido

RTPM Study guide based on actual test with correct answers
|\ |\ |\ |\ |\ |\ |\ |\ |\




1.Technology Responsibility Matrix: The technology responsibility |\ |\ |\ |\ |\ |\




matrix in- cludes key information about furnishings, the statement of
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\




work, technology sys- tems, and technology spaces. It does not,
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\




however, include information about the commissioning or QA plans.
|\ |\ |\ |\ |\ |\ |\ |\ |\




(TPMRM, page 1-24) |\ |\




2.Integration Management: Covers the breakup of a larger project to
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\




multiple small projects or conversely running several small projects as
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\




one . it also includes the integration of various sub-contractors into the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




organization under an integrated plan. |\ |\ |\ |\




3.Stakeholder management "Keep satisified": Client |\ |\ |\ |\ |\




President Financial sponsors |\ |\




cheif finance officer
|\ |\




|\ AHJ
general contractor. |\




4.Stakeholder management "Manage Closely": Board of |\ |\ |\ |\ |\ |\




directors client PM |\ |\




general contractor PM |\ |\




5.Stakenholder management "Monitor": |\ |\ |\




Architect Engineer |\




Sub contractors
|\ |\




Service providers |\




6.Stakeholder management "Keep Informed": design consultaint |\ |\ |\ |\ |\ |\


1 |\/ |\85

,(client) Department heads |\ |\




Community |\




advocates Client |\ |\




staff
Vendors |\




End user |\




7.OBS "Orgnization Breakdown Structure": Shows who is responsible for
|\ |\ |\ |\ |\ |\ |\ |\ |\




other team members. simular to a RACI chart regardless of the pay
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




scale or hierarchy
|\ |\




8.Work Breakdown Structure (WBS): It must cover the elements of the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




project's end product or deliverable and also all the elements of the
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




project, including: |\




1 Planning
2 Implementing the project |\ |\




3 Closing out the project. |\ |\ |\




It should be as specific as possible.
|\ |\ |\ |\ |\ |\




9.Work Breakdown Structure (WBS) Level 1 first position: Represents
|\ |\ |\ |\ |\ |\ |\ |\ |\




the overall deliverable of the project.
|\ |\ |\ |\ |\




10.Work Breakdown Structure (WBS) Second position: Represents
|\ |\ |\ |\ |\ |\ |\




summary tasks within the overall deliverable or project.
|\ |\ |\ |\ |\ |\ |\




2 |\/ |\85

,11.Work Breakdown Structure (WBS) Third position: Represents work
|\ |\ |\ |\ |\ |\ |\ |\




pack- ages that are discrete activities within each summary task within
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




the overall deliver- able of a project.
|\ |\ |\ |\ |\ |\




12.PERT developing a schedule finish to start: Finish -
|\ |\ |\ |\ |\ |\ |\ |\ |\




Start Pulling cable can't start until installing conduit
|\ |\ |\ |\ |\ |\ |\ |\




finishes
13.PERT developing a schedule Finish - Finish: finish -
|\ |\ |\ |\ |\ |\ |\ |\ |\




finish Labeling outlets cannot finish until testing finishes
|\ |\ |\ |\ |\ |\ |\




14.PERT developing a schedule Start - Start: Start -
|\ |\ |\ |\ |\ |\ |\ |\ |\




Start Bond basket tray cannot start until hang basket
|\ |\ |\ |\ |\ |\ |\ |\




|\ tray starts
|\




15.PERT developing a schedule Start - Finish: Start -
|\ |\ |\ |\ |\ |\ |\ |\ |\




Finish install fiber can not finish until ordered fiber
|\ |\ |\ |\ |\ |\ |\ |\ |\




starts
16.What are the three estimates used in PERT for each activity?:
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




Optimistic, Most Likely, |\ |\




Pessimistic
17.What does the Optimistic estimate represent in PERT?: Lowest
|\ |\ |\ |\ |\ |\ |\ |\ |\




projected cost or fastest time |\ |\ |\ |\




18.What does the Most Likely estimate represent in PERT?: Average
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\




project cost or time |\ |\ |\




19.What does the Pessimistic estimate represent in PERT?: Highest
|\ |\ |\ |\ |\ |\ |\ |\ |\




projected cost or longest timeframe |\ |\ |\ |\




20.PERT Calulation: (optimistic + (4 x Most Likey) + Pessimistic)/ 6 =
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\



3 |\/ |\85

, 21.EVM (Earned Value Management): A methodology that combines
|\ |\ |\ |\ |\ |\ |\ |\




scope, schedule, and resource measurements to assess project
|\ |\ |\ |\ |\ |\ |\ |\




performance and progress. |\ |\




22.EVM (Earned Value Management) calulation: EVM = (percentage
|\ |\ |\ |\ |\ |\ |\ |\




complete x total project budget) |\ |\ |\ |\




23.Using budget to Determine project Performance: Once project has
|\ |\ |\ |\ |\ |\ |\ |\ |\




been started 2 areas will be monitored
|\ |\ |\ |\ |\ |\




EV and AC. |\ |\




24.EV (BCWP): The measure of work performed in terms of the budget
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




authorized for the work. (amount of work completed for the project)
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




formally known as BCWP |\ |\ |\




25.AC (ACWP): Is the realized cost incurred for the work performed on an
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




|\ activity durning a specific time period.
|\ |\ |\ |\ |\




26.Developing a Communication Plan: Mostly reports and tasks who's |\ |\ |\ |\ |\ |\ |\ |\ |\




account- able is not part of this process. |\ |\ |\ |\ |\ |\ |\




27.kickoff meeting: A meeting used to initiate the start of the project;
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




typically attended by all the key stakeholders; can be done when
|\ |\ |\ |\ |\ |\ |\ |\ |\ |\ |\




Initiating or Planning is complete depending upon the organization. will
|\ |\ |\ |\ |\ |\ |\ |\ |\




|\ include contract documents such as the signed contract.
|\ |\ |\ |\ |\ |\ |\




4 |\/ |\85

Información del documento

Subido en
8 de julio de 2025
Número de páginas
85
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$25.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
EXAMSTUDYPLUG
4.5
(242)
Vendido
394
Seguidores
107
Artículos
21100
Última venta
6 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes