Erosion and Sediment Control Exam Questions And Answers Already Graded A+

Document preview thumbnail
Vista previa 3 fuera de 16 páginas

Erosion and Sediment Control Exam Questions And Answers Already Graded A+

Vista previa del contenido

Erosion and Sediment Control Exam
Questions And Answers Already Graded
A+
Minimum Standard 1 CORRECT ANSWERS Stabilization

permanent or temporary soil stabilization shall be applied to denuded areas within
seven days after final grade is reached on any portion of the site; temporary soil
stabilization shall be applied within seven days to denuded areas that may not be at
final grade but will remain dormant for longer than 14 days; permanent stabilization shall
be applied to areas that are to be left dormant for more than one year

Site NOT at Final Grade CORRECT ANSWERS - stabilize in 14 days
- temporarily seed
- mulch
- permanently stabilize if dormant > 1 year

Site at Final Grade CORRECT ANSWERS - stabilize in 7 days (recommended
immediately)
- permanently or temporarily seed and mulch
- mulch/matting/straw

Minimum Standard 2 CORRECT ANSWERS Stock Piles, Waste and Borrow Areas

during construction, soil stock piles and borrow areas shall be stabilized or protected
with sediment trapping measures

mulch prevents erosion by protecting the surface from raindrop impact and silt fence
intercepts and detains from disturbed areas

Minimum Standard 3 CORRECT ANSWERS Permanent Vegetation

permanent vegetation cover shall be established on denuded areas not otherwise
permanently stabilized (permanent vegetation shall not be considered established until
a ground cover is achieved that is uniform, mature enough to survive, and will inhibit
erosion *there is no % associated with this*)

reduce erosion and decrease sediment yield from disturbed area

this is the standard used to verify that a site is ready for release of bonds or surety

Minimum Standard 4 CORRECT ANSWERS First-Step Measures

,Sediment basins and traps, perimeter dikes, sediment barriers and other measures
intended to trap sediment shall be constructed as a first step in any land-disturbing
activity and shall be made functional before upslope land disturbance takes place

a certain amount of initial land disturbance may be required to provide access for
equipment to install the perimeter controls, but site clearing and grading should be kept
to a minimum until the perimeter controls are in place

intercepts and detains small amounts of sediment from disturbed areas during
construction operation to prevent sediment from leaving the site and decrease velocity
of sheet flows and low-to-moderate level channel flow

Perimeter Controls CORRECT ANSWERS assures that sediment does not leave the
perimeter of the land-disturbing area once site clearing, grading, and construction
commences

Examples: silt fences, sediment traps, sediment basins, construction entrance,
temporary diversions, diversions

Minimum Standard 5 CORRECT ANSWERS Earthen Structure Stabilization

stabilization measures shall be applied to earthen structures such as dams, dikes, and
diversions immediately after installation

reduce erosion and sedimentation and reduce damage from sediment and runoff to
downstream or off-site areas

Minimum Standard 6 CORRECT ANSWERS Traps and Basins

sediment traps and basins shall be designed and constructed based upon the total
drainage area (not just disturbed area) to be served by the trap or basin

Sediment Traps CORRECT ANSWERS minimum storage capacity shall be 134 cubic
yards per acre of drainage area and shall only control drainage areas less than 3 acres

*stone outlet = trap*

Sediment Basins CORRECT ANSWERS surface runoff from disturbed areas that is
comprised of flow from drainage areas greater than or equal to 3 acres shall be
controlled by a basin; minimum storage capacity of a sediment basin shall be 134 cubic
yards per acre of drainage area; the outfall system shall, at a minimum, maintain the
structural integrity of the basin during a 25-year storm of 24-hour duration; runoff
coefficients used in runoff calculations shall correspond to a bare earth condition or
those conditions expected to exist while the sediment basin is utilized.

, Sediment Trapping Devises CORRECT ANSWERS 1. place near the lowest drainage
points of a project

2. install as a first-step measure [MS-4]

3. stabilize immediately [MS-5]

4. must include outlet protection for basins [MS-11]

Minimum Standard 7 CORRECT ANSWERS Cut and Fill Slopes

roughening the surface of the slope decreases runoff, lowers the velocity runoff,
increases water retention, and leads to better seed germination

slopes that are found to be eroding excessively within on year of permanent stabilization
shall be provided with additional slop stabilizing measures until the problem is corrected

Minimum Standard 8 CORRECT ANSWERS Concentrated Runoff

shall not flow down cut or fill slopes unless contained within an adequate temporary or
permanent channel, flume or slope drain structure

outlets of these drains need outlet protection to prevent erosion from the concentrated
flow

size of pipe depends on drainage area

temporarily conduct concentrated stormwater runoff safely down the face of a cut or fill
slope without causing erosion on or below the slope

Minimum Standard 9 CORRECT ANSWERS Water Seeps

whenever water seeps from a slope face, adequate drainage or other protection shall be
provided

cut and fill operations may expose shallow aquifers or groundwater tables from which
water may seep through the side of a slope

Minimum Standard 10 CORRECT ANSWERS Inlet Protection

all storm sewer inlets that are made operable during construction shall be protected so
that sediment-laden water cannot enter the conveyance system without first being
filtered or otherwise treated to remove sediment

storm sewers are designed to efficiently transport stormwater away from the site, so
when sediment enters the storm sewer system, two negative effects can occur:

Información del documento

Subido en
23 de junio de 2025
Número de páginas
16
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$16.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
ElevatedExcellence
3.8
(178)
Vendido
951
Seguidores
505
Artículos
18297
Última venta
3 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes