CIS 440: SCRUM Exam questions with
complete solutions
When is a Sprint over? - correct answer ✔✔When the time-box expires.
Who is on the Scrum Team? - correct answer ✔✔- The Scrum Master
- The Product Owner
- The Development Team
Development team membership should change - correct answer ✔✔If needed, but productivity
will drop as new members adjust
Who has the final saw on the order of the product backlog - correct answer ✔✔product owner
The CEO asks for important item be added to the current sprint, what should the DEV team do?
- correct answer ✔✔Inform product owner so he/she can work with CEO
Who should know the most about progress toward a business objective or a release - correct
answer ✔✔The product owner
The purpose of a sprint is to produce a done increment of working product - correct answer
✔✔TRUE
Which statement best describes a product owner's responsibility - correct answer
✔✔Optimizing the value of the work the development team does
complete solutions
When is a Sprint over? - correct answer ✔✔When the time-box expires.
Who is on the Scrum Team? - correct answer ✔✔- The Scrum Master
- The Product Owner
- The Development Team
Development team membership should change - correct answer ✔✔If needed, but productivity
will drop as new members adjust
Who has the final saw on the order of the product backlog - correct answer ✔✔product owner
The CEO asks for important item be added to the current sprint, what should the DEV team do?
- correct answer ✔✔Inform product owner so he/she can work with CEO
Who should know the most about progress toward a business objective or a release - correct
answer ✔✔The product owner
The purpose of a sprint is to produce a done increment of working product - correct answer
✔✔TRUE
Which statement best describes a product owner's responsibility - correct answer
✔✔Optimizing the value of the work the development team does