Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 3 fuera de 26 páginas
Examen

CSLB Practice Law B | Exam Revision Questions and Correct Answers With 100% Correct Answers | Latest 2025 Update.

Document preview thumbnail
Vista previa 3 fuera de 26 páginas

CSLB Practice Law B | Exam Revision Questions and Correct Answers With 100% Correct Answers | Latest 2025 Update.

Vista previa del contenido

CSLB Practice Law B | Exam Revision Questions and Correct Answers With
100% Correct Answers | Latest 2025 Update.



A subcontractor or material supplier has _____ days to file a lien once a notice of completion has
been recorded. - ANSWER- 30


How must a client submit a claim for service or repair of a defect on fit and finish items after a
remodel? - ANSWER- By certified mail


By overnight mail


By personal delivery


A contractor meets Mr. Jones at his home to discuss remodeling. The contractor and Mr. Jones sign
a contract that includes a three-day cancellation form. After the contractor leaves, Mr. Jones
decides not to have the work done. Instead of using the cancellation form, Mr. Jones sends the
contractor a letter by first-class mail stating that he is canceling the contract. Is Mr. Jones'
cancellation effective? - ANSWER- Yes. Mr. Jones' letter does cancel the contract because it
indicates his intention not to be bound by the contract.


If a contractor forgets to renew his or her license on time, the expired license may be renewed any
time within _____ after its expiration without reapplying for a license and fulfilling the exam or
waiver requirements again. - ANSWER- Five years


You are the qualifier for an active contractor's license. How do you inactivate the license? -
ANSWER- Write to the CSLB, requesting that the license be made inactive.


When a subcontractor does work on a public works contract, the public agency considers the
subcontractor to be: - ANSWER- a subcontractor of the prime contractor

,A contractor hires a subcontractor to demolish a concrete wall. Who is responsible for supplying
safety goggles? - ANSWER- subcontractor


Sometimes contracts prove to be too vague to interpret without disagreement between owner and
contractor. Which of the following steps would best prevent such problems? - ANSWER-
Review the plans and specifications with the owner.


A contractor is looking for an insurance policy to cover a high degree of exposure to risk. Of the
following, which policy would be best for this purpose? - ANSWER- umbrella



To whom do you report and pay sales tax? - ANSWER- Board of Equalization



The federal Employer Identification Number (EIN) is issued by the: - ANSWER- Internal
Revenue Service


When purchasing insurance, what is the best way to choose among different companies? -
ANSWER- cost and coverage


As required by the Immigration Reform and Control Act, all employees hired on or after November
7, 1986 must complete Form _____ to verify their employment eligibility status. - ANSWER-
I-9


If required safety devices are missing from tools, what should an employee do? - ANSWER-
Notify the contractor, who is responsible for safety.


Of the following, which document is usually delivered first in a transaction involving a home
improvement contract? - ANSWER- "Notice to Owner"


Who is ultimately responsible for seeing that safety equipment is actually put to use on the jobsite?
- ANSWER- contractor

, A mechanics' lien is a written document that must be signed and verified by the claimant. The first
and third steps a contractor should take in filing a lien are listed below. Step 1: Obtain the exact
legal description of the property. Step 2: Step 3: Find out if the person requesting the work of
improvement is the owner. What is Step 2? - ANSWER- Find out the name of the legal owner
of the property as well as the percent of ownership.


A(n) _____ represents a company's financial position on a specified date. - ANSWER- balance
sheet


When you get an approved set of plans, what should you do first? - ANSWER- Read any notes
from the building department.


When bidding on work, which of the following would you NOT include in the price of your bid?
- ANSWER- worker's compensation insurance premium



The purpose of a "Preliminary 20-day Notice" for private work is to: - ANSWER- notify the
property owner that the subcontractor or firm who sent the notice will be making improvements
on the property


When should you let your attorney see a construction contract? - ANSWER- After the contract
is prepared, but before you sign it.


When is an employee allowed to view their own personnel file? - ANSWER- whenever they
wish to


Before beginning work, an employer or contractor must inquire whether asbestos is present in any
building constructed prior to: - ANSWER- 1978



Is it legal for a contractor to require employees to take lie detector tests? - ANSWER- It is not
legal for the contractor to require lie detector tests, but it would be legal for a federal, state, or local
public agency to require lie detector tests of their employees.

Información del documento

Subido en
2 de junio de 2025
Número de páginas
26
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$13.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
LECTpharis
4.8
(8)
Vendido
41
Seguidores
1
Artículos
6040
Última venta
2 meses hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes