(T/F) A milestone schedule may be expressed as contract days. - ANSWER-T
(T/F) A typical construction contingency is 20% - ANSWER-F
(T/F) All 50 states require an NAAB accredited degree for licensing. - ANSWER-F
(T/F) An architect's approval of a submittal that differs from the specified item(s) relieves
the contractor from the responsibility to conform to the contract documents. - ANSWER-
F
(T/F) Detailed cost estimates are part of basic services in the AIA B101-2017. -
ANSWER-F
(T/F) During construction, the architect is the final decision maker on aesthetics -
ANSWER-T
(T/F) Each firm has their own way of breaking down the different technical specifications
in a project manual as there is no industry standard. - ANSWER-F
(T/F) If the architect specifies door hardware that does not meet the building code and
has to be changed after it is installed, it would be considered an omission. - ANSWER-F
(T/F) In construction scheduling a successor is something that must happen before
another construction activity. - ANSWER-F
(T/F) In the AIA B101-2017, during constructions, the architect is required to inspect the
work and guarantee that it is complete. - ANSWER-F
(T/F) In the AXP for 100% Credit, 6 months experience is the maximum that can be
reported in one submission and this must be submitted within 8 months of when the
experience started. - ANSWER-T
(T/F) Inflation outpaces construction escalation. - ANSWER-F
(T/F) One of the uses of the Schedule of Values is to assist the architect in determining
how complete a project is and therefore how much the contractor should be paid. -
ANSWER-T
(T/F) Product warranties begin at Substantial Completion. - ANSWER-T
(T/F) Studies prove that QBS consistently delivers lower overall costs and reduced
change orders. - ANSWER-T
(T/F) A milestone schedule may be expressed as contract days. - ANSWER-T
(T/F) A typical construction contingency is 20% - ANSWER-F
(T/F) All 50 states require an NAAB accredited degree for licensing. - ANSWER-F
(T/F) An architect's approval of a submittal that differs from the specified item(s) relieves
the contractor from the responsibility to conform to the contract documents. - ANSWER-
F
(T/F) Detailed cost estimates are part of basic services in the AIA B101-2017. -
ANSWER-F
(T/F) During construction, the architect is the final decision maker on aesthetics -
ANSWER-T
(T/F) Each firm has their own way of breaking down the different technical specifications
in a project manual as there is no industry standard. - ANSWER-F
(T/F) If the architect specifies door hardware that does not meet the building code and
has to be changed after it is installed, it would be considered an omission. - ANSWER-F
(T/F) In construction scheduling a successor is something that must happen before
another construction activity. - ANSWER-F
(T/F) In the AIA B101-2017, during constructions, the architect is required to inspect the
work and guarantee that it is complete. - ANSWER-F
(T/F) In the AXP for 100% Credit, 6 months experience is the maximum that can be
reported in one submission and this must be submitted within 8 months of when the
experience started. - ANSWER-T
(T/F) Inflation outpaces construction escalation. - ANSWER-F
(T/F) One of the uses of the Schedule of Values is to assist the architect in determining
how complete a project is and therefore how much the contractor should be paid. -
ANSWER-T
(T/F) Product warranties begin at Substantial Completion. - ANSWER-T
(T/F) Studies prove that QBS consistently delivers lower overall costs and reduced
change orders. - ANSWER-T