CIVIL ENGINEERING
INTERNSHIP REPORT SAMPLE
THE UNIVERSITY OF LAHORE
DEPARTMENT OF CIVIL ENGINEERING
INTERNSHIP REPORT
NAME: MUHAMMAD FAROOQ
REGISTRATION No.: BSCE 01143009
ADVISOR: Dr. AMIR FAROOQ
SPONSORING COMPANY: WAREESHA ENTERPRISES
Project Name:
House Construction of Proposed 3 Units of 2 Kanal Villas (Phase 2) At Phase VI, DHA
Lahore
Duration: 2nd June 2017 to 1st July 2017
Date of Submission: 17th November 2017
, Acknoldgment
ACKNOLDGEMENT
The field of construction has always been a source of inspiration for me during
my entire academic career. To work in a construction site, to acquaint with its
working mechanism was always a point of interest for me and Allah gave me a
golden opportunity to complete my internship at House Construction of
Proposed 3 Units of 2 Kanal Villas (Phase 2) At Phase VI, DHA Lahore with
WAREESHA ENTERPRISES. I had a general idea about the construction site,
but once I practically started the internship in construction field I observed much
about site. I learned a lot about the overall construction arena. This expanded my
vision about the construction sector.
This report is a thorough essence of my rigorous studies which I undergone
through in a period of 04 weeks in DEFENCE RAYA GOLF & COUNTRY
CLUB
I have exclusively studied and observed the operations/ functioning of the
company and tried my best to abreast myself with all the dimensions of the
company. The purpose of this report is to evaluate the performance of
WAREESHA ENTERPRISES in diversified avenues and give concrete
recommendation for further improvement. Although the company is functioning
satisfactory, but the path to ultimate success is still full of threats and hurdles. It
was a great experience to work there and to be a significant part of the company.
, Index
Table of Contents
Chapter # 1 ........................................................................................................................... 1
Introduction .......................................................................................................................... 1
1.1. Project Description: ................................................................................................... 1
1.2. Introduction to Organization: .................................................................................... 1
1.2.1) Introduction of Staff Members: ...................................................................... 2
1.2.2) Organization Department ............................................................................... 2
1.2.3) Machinery ...................................................................................................... 2
1.2.4) Some Previous Projects: ................................................................................. 3
Chapter # 2 ........................................................................................................................... 4
Activities Participated: ......................................................................................................... 4
2.1. Schedule of Internship:.............................................................................................. 4
2.2. Site Work: ................................................................................................................. 4
2.3. Section of the Company I Was Working In: ............................................................. 4
2.4. Summary of Office Work Activities: ........................................................................ 4
2.5. Excavation for Footing .............................................................................................. 5
2.6. Lean Concrete: .......................................................................................................... 5
2.7. Steel Fixing For Footing ........................................................................................... 6
2.8. Steel Fixing In Footing and Column: ........................................................................ 6
2.9. Concrete Pouring In Footing And Column: .............................................................. 6
2.10. Back Filling ............................................................................................................... 6
2.11. Retaining Walls in Foundations: ............................................................................... 7
2.12. Construction Material:............................................................................................... 7
2.13. Details of Ground Floor: ........................................................................................... 7
2.14. My Duties and Responsibilities: ................................................................................ 8
Chapter # 3 ......................................................................................................................... 10
Activities Observed ............................................................................................................ 10
, Index
3.1) Concrete Work: ....................................................................................................... 10
3.2) Concrete Making Materials: .................................................................................... 11
3.2.1) Aggregate: .................................................................................................... 11
3.2.2) Sand:............................................................................................................. 11
3.2.3) Cement: ........................................................................................................ 11
Chapter # 4 ......................................................................................................................... 12
Correlation of Activities with Standards ............................................................................ 12
4.1. For Slump of Hydraulic Cement Concrete:............................................................. 12
Results Of Slump In Field: ......................................................................................... 12
4.2. Standard Test Method For Rebound Number Of Hardened Concrete: ................... 13
4.3. For Reinforcement:.................................................................................................. 14
4.4. For Concrete Mix Design:....................................................................................... 15
Chapter # 5 ......................................................................................................................... 16
Study of Drawings .............................................................................................................. 16
5.1. Some Drawings Specifications: ............................................................................... 16
5.1.1. Lap Length: .................................................................................................. 16
5.1.2. Structural Element (Aggregate Size): .......................................................... 16
5.1.3. Concrete Protection to Reinforcement: ........................................................ 17
Chapter # 6 ......................................................................................................................... 18
Difficulties Faced ............................................................................................................... 18
Chapter # 7 ......................................................................................................................... 19
Summary and Knowledge Gained ..................................................................................... 19
Appendix ............................................................................................................................ 20
List of Figures
Figure 1: Ground Floor Plan .............................................................................................. 20
INTERNSHIP REPORT SAMPLE
THE UNIVERSITY OF LAHORE
DEPARTMENT OF CIVIL ENGINEERING
INTERNSHIP REPORT
NAME: MUHAMMAD FAROOQ
REGISTRATION No.: BSCE 01143009
ADVISOR: Dr. AMIR FAROOQ
SPONSORING COMPANY: WAREESHA ENTERPRISES
Project Name:
House Construction of Proposed 3 Units of 2 Kanal Villas (Phase 2) At Phase VI, DHA
Lahore
Duration: 2nd June 2017 to 1st July 2017
Date of Submission: 17th November 2017
, Acknoldgment
ACKNOLDGEMENT
The field of construction has always been a source of inspiration for me during
my entire academic career. To work in a construction site, to acquaint with its
working mechanism was always a point of interest for me and Allah gave me a
golden opportunity to complete my internship at House Construction of
Proposed 3 Units of 2 Kanal Villas (Phase 2) At Phase VI, DHA Lahore with
WAREESHA ENTERPRISES. I had a general idea about the construction site,
but once I practically started the internship in construction field I observed much
about site. I learned a lot about the overall construction arena. This expanded my
vision about the construction sector.
This report is a thorough essence of my rigorous studies which I undergone
through in a period of 04 weeks in DEFENCE RAYA GOLF & COUNTRY
CLUB
I have exclusively studied and observed the operations/ functioning of the
company and tried my best to abreast myself with all the dimensions of the
company. The purpose of this report is to evaluate the performance of
WAREESHA ENTERPRISES in diversified avenues and give concrete
recommendation for further improvement. Although the company is functioning
satisfactory, but the path to ultimate success is still full of threats and hurdles. It
was a great experience to work there and to be a significant part of the company.
, Index
Table of Contents
Chapter # 1 ........................................................................................................................... 1
Introduction .......................................................................................................................... 1
1.1. Project Description: ................................................................................................... 1
1.2. Introduction to Organization: .................................................................................... 1
1.2.1) Introduction of Staff Members: ...................................................................... 2
1.2.2) Organization Department ............................................................................... 2
1.2.3) Machinery ...................................................................................................... 2
1.2.4) Some Previous Projects: ................................................................................. 3
Chapter # 2 ........................................................................................................................... 4
Activities Participated: ......................................................................................................... 4
2.1. Schedule of Internship:.............................................................................................. 4
2.2. Site Work: ................................................................................................................. 4
2.3. Section of the Company I Was Working In: ............................................................. 4
2.4. Summary of Office Work Activities: ........................................................................ 4
2.5. Excavation for Footing .............................................................................................. 5
2.6. Lean Concrete: .......................................................................................................... 5
2.7. Steel Fixing For Footing ........................................................................................... 6
2.8. Steel Fixing In Footing and Column: ........................................................................ 6
2.9. Concrete Pouring In Footing And Column: .............................................................. 6
2.10. Back Filling ............................................................................................................... 6
2.11. Retaining Walls in Foundations: ............................................................................... 7
2.12. Construction Material:............................................................................................... 7
2.13. Details of Ground Floor: ........................................................................................... 7
2.14. My Duties and Responsibilities: ................................................................................ 8
Chapter # 3 ......................................................................................................................... 10
Activities Observed ............................................................................................................ 10
, Index
3.1) Concrete Work: ....................................................................................................... 10
3.2) Concrete Making Materials: .................................................................................... 11
3.2.1) Aggregate: .................................................................................................... 11
3.2.2) Sand:............................................................................................................. 11
3.2.3) Cement: ........................................................................................................ 11
Chapter # 4 ......................................................................................................................... 12
Correlation of Activities with Standards ............................................................................ 12
4.1. For Slump of Hydraulic Cement Concrete:............................................................. 12
Results Of Slump In Field: ......................................................................................... 12
4.2. Standard Test Method For Rebound Number Of Hardened Concrete: ................... 13
4.3. For Reinforcement:.................................................................................................. 14
4.4. For Concrete Mix Design:....................................................................................... 15
Chapter # 5 ......................................................................................................................... 16
Study of Drawings .............................................................................................................. 16
5.1. Some Drawings Specifications: ............................................................................... 16
5.1.1. Lap Length: .................................................................................................. 16
5.1.2. Structural Element (Aggregate Size): .......................................................... 16
5.1.3. Concrete Protection to Reinforcement: ........................................................ 17
Chapter # 6 ......................................................................................................................... 18
Difficulties Faced ............................................................................................................... 18
Chapter # 7 ......................................................................................................................... 19
Summary and Knowledge Gained ..................................................................................... 19
Appendix ............................................................................................................................ 20
List of Figures
Figure 1: Ground Floor Plan .............................................................................................. 20