UMD is a public university Contract Documents
that recently completed a
bidding process for a new
academic center. Most of
the bid documents will
become ___ that define
the legal terms of the
contract. The contracts
between GC's and
subcontractors typically
reference these
documents.
A variety of separate General Conditions, Agreement, Drawings and
documents typically Specifications, Agenda and Modifications (NOT
comprise the contract Differing Site COnditions)
documents. Select all of
the following that are
generally included
1/18
,4/7/25, 9:44 PM ENCE 325 Final
The agreement consists of Exclusions
facts about the project,
and it is the most
important document
taking precedence over
all others. It provides the
GC an opportunity to
identify problematic or ill-
defined items that they
don't want to be
responsible for. These
items are referred to as
______.
General COnditions General Provisions, Protection of Persons and
outline the rights and Property, Insurance and Bonds, Termination of
responsibilities of the Suspension of the COntract (NOT Design Guidelines)
Owner, Designer, and
Contractor. For vertical
construction (buildings),
the AIA provides a
standard form of General
Conditions in "A201"
including 15 articles
addressing the terms for
changing work,
procedures of Contractor
Payment, dealing with
disputes and delays, and
more. Select all of the
other applicable articles in
"A201"`
Supplementary Conditions true
modify the general
conditions and add
information specific to a
particular job
2/18
, 4/7/25, 9:44 PM ENCE 325 Final
Specifications are an Quality assurance, submittals, quality of materials and
important part of Contract products, special installation requirements (NOT
Documents as they Subcontractor Names and Numbers)
describe in written form
information that cannot be
conveyed by Drawings
alone. Select all of the
applicable aspects of
Specifications that
Architects provide for
GC's to order the proper
products and materials
and accurately assess the
labor necessary for work.
The COnstruction Division 03, Division 04
Specifications Institute
(CSI) developed the
MasterFormat standard for
organizing contract
specifications. Up to the
year 2004, MasterFormat
provided 16 divisions of
work. What are the two
applicable divisions for
Concrete and Masonry
work?
UMD selects JW builders Determining the means and methods of construction,
as the GC to build a new jobsite layout plan, creating a master construction
Academic center. Select schedule, pre-construction meeting (NOT submitting
all of the typical pre- bid estimates)
construction activities the
GC will handle before
work begins.
3/18