1. What is the primary purpose of a project charter?

A. To define the project scope

B. To authorize the project and provide a high-level overview

C. To assign tasks to the project team

D. To establish project deadlines

Answer: B) To authorize the project and provide a high-level overview

Rationale: A project charter formally authorizes the project, providing an overview of

the project's objectives, stakeholders, and high-level requirements.




2. Which of the following is the first phase in the project management lifecycle?

A. Planning

B. Execution

C. Initiating

D. Closing

Answer: C) Initiating

Rationale: The initiating phase is where the project is formally authorized and defined

at a high level.

,3. Which of the following techniques is used to identify project risks?

A. SWOT analysis

B. Monte Carlo simulation

C. PERT diagram

D. Gantt chart

Answer: A) SWOT analysis

Rationale: SWOT analysis (Strengths, Weaknesses, Opportunities, Threats) is

commonly used to identify and evaluate potential risks in projects.




4. What does the acronym "WBS" stand for?

A. Work Breakdown Structure

B. Work Base Schedule

C. Wide Base Scope

D. Work Boundary System

Answer: A) Work Breakdown Structure

Rationale: WBS is a hierarchical decomposition of the total scope of work to

accomplish the project objectives and deliverables.

, 5. A project manager is focusing on delivering a project within scope, time, and cost

constraints. This is an example of managing which of the following?

A. Project procurement

B. Project triple constraint

C. Project stakeholders

D. Project communication

Answer: B) Project triple constraint

Rationale: The project triple constraint refers to the balance of scope, time, and cost,

which must be managed to deliver a successful project.




6. Which document is used to outline the project’s schedule and timeline?

A. Risk register

B. Gantt chart

C. Scope statement

D. Resource plan

Answer: B) Gantt chart

Rationale: A Gantt chart is a visual timeline used for planning and tracking project

schedules.

Información del documento

Subido en
17 de marzo de 2025
Número de páginas
29
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$10.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
douglasmugwe82
5.0
(1)
Vendido
2
Seguidores
0
Artículos
4215
Última venta
1 año hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes