1. Which of the following is an example of a quantitative risk analysis technique?

A. SWOT analysis

B. Monte Carlo simulation

C. Brainstorming

D. Delphi technique

Answer: B) Monte Carlo simulation

Rationale: Monte Carlo simulation is a quantitative risk analysis technique used to

predict the probability of different outcomes in a project by running simulations based

on input variables.




2. What is the main difference between project management and operations

management?

A. Project management is concerned with ongoing work, while operations

management is focused on temporary projects

B. Project management focuses on managing resources, while operations management

focuses on scheduling tasks

,C. Project management deals with temporary projects, while operations management

deals with ongoing, routine activities

D. There is no significant difference

Answer: C) Project management deals with temporary projects, while operations

management deals with ongoing, routine activities

Rationale: Project management focuses on specific, temporary projects, while

operations management focuses on continuous, ongoing work.




3. What is "resource smoothing"?

A. Optimizing project cost by allocating more resources

B. Adjusting project schedules to minimize resource conflicts without changing the

project's duration

C. Overallocating resources to accelerate project completion

D. Reducing project scope to ensure better resource utilization

Answer: B) Adjusting project schedules to minimize resource conflicts without

changing the project's duration

Rationale: Resource smoothing involves adjusting the project schedule to ensure that

resources are used efficiently without extending the project duration.

,4. What is the primary benefit of using a project management software tool?

A. It ensures all stakeholders are involved in every decision

B. It helps automate administrative tasks like scheduling, cost tracking, and

communication

C. It eliminates the need for a project manager

D. It reduces the need for team collaboration

Answer: B) It helps automate administrative tasks like scheduling, cost tracking, and

communication

Rationale: Project management software aids in automating and streamlining tasks

such as scheduling, resource management, and progress tracking.




5. What does the "fishbone diagram" (Ishikawa) help identify in a project?

A. The root causes of problems

B. The project schedule

C. The project stakeholders

D. The project’s critical path

Answer: A) The root causes of problems

Rationale: A fishbone diagram is a tool used for identifying the root causes of issues

in a project or process.

, 6. A project manager is focusing on delivering a project within scope, time, and cost

constraints. This is an example of managing which of the following?

A. Project procurement

B. Project triple constraint

C. Project stakeholders

D. Project communication

Answer: B) Project triple constraint

Rationale: The project triple constraint refers to the balance of scope, time, and cost,

which must be managed to deliver a successful project.




7. A project manager identifies a risk and decides to avoid it by changing the project

scope. What risk response strategy is this?

A. Mitigation

B. Avoidance

C. Acceptance

D. Transfer

Answer: B) Avoidance

Información del documento

Subido en
17 de marzo de 2025
Número de páginas
61
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$10.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
douglasmugwe82
5.0
(1)
Vendido
2
Seguidores
0
Artículos
4215
Última venta
1 año hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes