• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 4 fuera de 41 páginas
Examen

WGU Project Management C722 Questions with verified answers'

Document preview thumbnail
Vista previa 4 fuera de 41 páginas

WGU Project Management C722 Questions with verified answers

Vista previa del contenido

WGU Project Management C722 Questions with
verified answers
A firm begins a strategic business initiative of developing a new business model
that will allow the firm to deliver an efficient, tailored service to its customers.


Which stakeholder would have triggered this strategic business initiative?


a. Director of operations




b. Production supervisor




c. Project sponsor




d. Financial controller Ans✓✓✓ c. Project sponsor


A firm begins its strategic business initiative of developing a new business model
that will allow the firm to deliver an efficient, tailored service to its customers. To
accomplish this, the firm initiates a business management project.


Which aspect of project management applies to this firm's project?

,a. Independent operations




b. Interdependent tasks




c. Regulatory concept




d. External environment Ans✓✓✓ b. interdependent tasks


A firm begins its strategic business initiative of developing a new business model
to enhance its competitiveness.


What can be identified as a strategic business initiative for this firm?


a. Timely payment of liabilities




b. Liaison with regulatory agencies




c. Improvement in product design

,d. Environmental scanning Ans✓✓✓ c. Improvement in product design


A general contractor from Germany is managing a construction project in Norway
that will add a new conference room to an existing office building. The project
needs to collect requirements from the client prior to developing plans to build
the new conference room.


Which two actions would prove useful to plan the project's quality?


Choose 2 answers


a. Defining traceable and verifiable requirements that can be validated at project
closure


b. establishing metrics that describe what to measure and how to measure it


c. Using inventory to protect against defects during project implementation


d. Changing the work plan to account for the project experiencing common
variation


e. Using slogans and numerical quotas to exhort resources to work harder
Ans✓✓✓ a. Defining traceable and verifiable requirements that can be validated
at project closure


b. establishing metrics that describe what to measure and how to measure it

, A general contractor is managing a construction project that will add a new
conference room to an existing office building. The project was documented in a
fixed-price contract that specified a completion date. The contract includes a
damages clause imposing a late completion penalty if the conference room is not
ready for use by the due date. One month into the implementation, the customer
wants to modify the room's lighting equipment. The requested change will delay
the project's critical path by three months.


Which process should be used to maintain the existing baseline?


a. Using a change management system to influence performance


b. Absorbing the change request in the baselines for time and cost


c. Focusing on the original scope


d. Using the risk management system to process change requests Ans✓✓✓ a.
using change management to influence performance


A general contractor is managing a highway construction project that will repair a
flood-damaged road. The Department of Transportation offered an incentive fee
if the repairs are completed early. Therefore, the project manager has established
a rewards and recognition program and has communicated this program to the
project team members. The project's recognition program will reward project
team members who add value by accelerating the project while maintaining its
ability to deliver the completed scope correctly.

Información del documento

Subido en
28 de febrero de 2025
Número de páginas
41
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$17.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
cracker
3.8
(401)
Vendido
2175
Seguidores
1346
Artículos
50090
Última venta
2 días hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes