S-12 Citywide Sprinkler Systems | S12 Sprinkler Test (Latest 2025/2026) with Verified Answers |100% Correct.

Document preview thumbnail
Vista previa 4 fuera de 33 páginas

What is a fire hydrant? A valve connection on a water supply system having one or more outlets and that is used to supply hose and fire department connections with water. The __________ is responsible to maintain sprinkler sys. and to determine qualifications. owner What is the purpose of gate valves? A valve controlling flow to water based fire protection systems. Is used to isolate,shut off, and open sprinkler systems. A _______ shall be required to post tags at main control valve and any sectional valves. master fire suppression piping contractor __________ shall be posted on the tag indicating both static and flow pressures before and after. drain test results Green tags indicate that __________. no impairment was found Green tags will be placed on the ____________. main control valve Systems partially or fully out of service shall have a ____________ tag placed on the main control valve. red A _________ disc of 8-9 inches shall be placed on connections to indicate the system is fully out of service. white A ________ disc of 8-9 inches shall be placed on connections to indicate the system is partially out of service. blue The impairment coordinator will notify the ___________ carrier, central station and occupants. insurance Records of all inspections and mx shall be maintained on premises for a min. of __________ years. 3 The building owner shall assign a(n) ____________ to comply with requirements. impairment coordinator Regular mx and minor repairs not affecting more than ________ floor(s) are considered planned removal from service. 1 Shutdowns affecting more than _________ floor(s) are considered unplanned out of service conditions. 1 Notification to fdny is not required, provided system is returned to service within ______ hours. 8

Vista previa del contenido

S-12 Citywide Sprinkler Systems | S12 i,- i,- i,- i,- i,- i,-




Sprinkler Test (Latest 2025/2026) with i,- i,- i,- i,- i,-




Verified Answers |100% Correct. i,- i,- i,-




What is a fire hydrant? A valve connection on a water supply
i,- i,- i,- i,- i,-i,- i,- i,- i,- i,- i,- i,- i,- i,-



system having one or more outlets and that is used to supply
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



hose and fire department connections with water.
i,- i,- i,- i,- i,- i,-




The __________ is responsible to maintain sprinkler sys. and to
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



determine qualifications. owner i,- i,-i,- i,-




What is the purpose of gate valves?
i,- i,-A valve controlling flow
i,- i,- i,- i,- i,-i,- i,- i,- i,- i,- i,-



to water based fire protection systems. Is used to isolate,shut off,
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



and open sprinkler systems.
i,- i,- i,-




A _______ shall be required to post tags at main control valve and
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



any sectional valves.
i,- master fire suppression piping contractor i,- i,-i,- i,- i,- i,- i,- i,-




__________ shall be posted on the tag indicating both static and
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



flow pressures before and after.
i,- drain test results i,- i,- i,- i,-i,- i,- i,- i,-




Green tags indicate that __________.
i,- i,- i,- i,- i,-i,- i,- no impairment was found
i,- i,- i,-

,Green tags will be placed on the ____________.
i,- i,- i,- i,- i,- i,- i,- i,-i,- i,- main control i,- i,-



valve


Systems partially or fully out of service shall have a ____________
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



tag placed on the main control valve.
i,- red
i,- i,- i,- i,- i,- i,-i,- i,-




A _________ disc of 8-9 inches shall be placed on connections to
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



indicate the system is fully out of service.
i,- white
i,- i,- i,- i,- i,- i,- i,-i,- i,-




A ________ disc of 8-9 inches shall be placed on connections to
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



indicate the system is partially out of service.
i,- blue
i,- i,- i,- i,- i,- i,- i,-i,- i,-




The impairment coordinator will notify the ___________ carrier,
i,- i,- i,- i,- i,- i,- i,- i,-



central station and occupants.
i,- insurance i,- i,- i,-i,- i,-




Records of all inspections and mx shall be maintained on
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



premises for a min. of __________ years.
i,- 3 i,- i,- i,- i,- i,- i,-i,- i,-




The building owner shall assign a(n) ____________ to comply with
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



requirements. impairment coordinator i,-i,- i,- i,-

,Regular mx and minor repairs not affecting more than ________
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



floor(s) are considered planned removal from service.
i,- i,- 1 i,- i,- i,- i,- i,-i,- i,-




Shutdowns affecting more than _________ floor(s) are considered
i,- i,- i,- i,- i,- i,- i,- i,-



unplanned out of service conditions. 1 i,- i,- i,- i,- i,-i,- i,-




Notification to fdny is not required, provided system is returned
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



to service within ______ hours.
i,- 8 i,- i,- i,- i,-i,- i,-




For unplanned removal from service, the cof holder shall
i,- i,- i,- i,- i,- i,- i,- i,- i,-



immediately report condition to the ___________ and the fire dept.
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-i,-



owner of the building
i,- i,- i,- i,-




If a minor defect is observed, it shall be corrected within _________
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



days or it will be considered an impairment.
i,- i,- i,- 30 i,- i,- i,- i,- i,-i,- i,-




What does "oos" stand for? i,- i,- i,- i,- i,-i,- i,- out of service
i,- i,-




Oos systems shall be identified by placing ________ at fire dept.
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



connections, sys. control valves, and fire command center i,- i,- i,- i,- i,- i,- i,- i,-i,- i,-



tags

, Prior to returning a sys. to service, the ___________ shall ensure that
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



necessary tests and inspections are conducted. i,- impairment i,- i,- i,- i,- i,-i,- i,- i,-



coordinator


Glycerin not greater than _________ percent or glycol not greather
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



than ________ percent shall be used to protect from freezing.
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-i,- i,-



50, 40
i,-




The cof number and signature of cof holder shall be posted near
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



the ____________.
i,- main control valve i,-i,- i,- i,- i,-




__________ shall be readily available to any representative of the
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



fire dept. these are to be maintained on site for 3 years.
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-i,- i,-



records


Failure to make inspections may result in __________ of the cof and
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



court proceedings. i,-revocation i,-i,- i,-




The cof holder may inspect, test, and perform routine mx if they
i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,- i,-



hold the following certs:
i,- refrigeration operating engineer,
i,- i,- i,-i,- i,- i,- i,- i,-



high pressure operating engineer, and nys high pressure
i,- i,- i,- i,- i,- i,- i,- i,-



operating engineer. i,-

Información del documento

Subido en
12 de enero de 2025
Número de páginas
33
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$11.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
AcademiaExpert
3.8
(519)
Vendido
2021
Seguidores
767
Artículos
4546
Última venta
9 horas hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes