• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 3 fuera de 21 páginas
Examen

Erosion and Sediment Control Exam Questions and Correct Answers Latest Update 2024 ( Already Passed)

Document preview thumbnail
Vista previa 3 fuera de 21 páginas

Erosion and Sediment Control Exam Questions and Correct Answers Latest Update 2024 ( Already Passed) Minimum Standard 1 - Answers Stabilization permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final grade is reached on any portion of the site; temporary soil stabilization shall be applied within seven days to denuded areas that may not be at final grade but will remain dormant for longer than 14 days; permanent stabilization shall be applied to areas that are to be left dormant for more than one year Site NOT at Final Grade - Answers - stabilize in 14 days - temporarily seed - mulch - permanently stabilize if dormant 1 year Site at Final Grade - Answers - stabilize in 7 days (recommended immediately) - permanently or temporarily seed and mulch - mulch/matting/straw Minimum Standard 2 - Answers Stock Piles, Waste and Borrow Areas during construction, soil stock piles and borrow areas shall be stabilized or protected with sediment trapping measures mulch prevents erosion by protecting the surface from raindrop impact and silt fence intercepts and detains from disturbed areas Minimum Standard 3 - Answers Permanent Vegetation permanent vegetation cover shall be established on denuded areas not otherwise permanently stabilized (permanent vegetation shall not be considered established until a ground cover is achieved that is uniform, mature enough to survive, and will inhibit erosion *there is no % associated with this*) reduce erosion and decrease sediment yield from disturbed area this is the standard used to verify that a site is ready for release of bonds or surety Minimum Standard 4 - Answers First-Step Measures Sediment basins and traps, perimeter dikes, sediment barriers and other measures intended to trap sediment shall be constructed as a first step in any land-disturbing activity and shall be made functional before upslope land disturbance takes place a certain amount of initial land disturbance may be required to provide access for equipment to install the perimeter controls, but site clearing and grading should be kept to a minimum until the perimeter controls are in place intercepts and detains small amounts of sediment from disturbed areas during construction operation to prevent sediment from leaving the site and decrease velocity of sheet flows and low-to-moderate level channel flow Perimeter Controls - Answers assures that sediment does not leave the perimeter of the land-disturbing area once site clearing, grading, and construction commences Examples: silt fences, sediment traps, sediment basins, construction entrance, temporary diversions, diversions Minimum Standard 5 - Answers Earthen Structure Stabilization stabilization measures shall be applied to earthen structures such as dams, dikes, and diversions immediately after installation reduce erosion and sedimentation and reduce damage from sediment and runoff to downstream or off-site areas Minimum Standard 6 - Answers Traps and Basins sediment traps and basins shall be designed and constructed based upon the total drainage area (not just disturbed area) to be served by the trap or basin Sediment Traps - Answers minimum storage capacity shall be 134 cubic yards per acre of drainage area and shall only control drainage areas less than 3 acres *stone outlet = trap* Sediment Basins - Answers surface runoff from disturbed areas that is comprised of flow from drainage areas greater than or equal to 3 acres shall be controlled by a basin; minimum storage capacity of a sediment basin shall be 134 cubic yards per acre of drainage area; the outfall system shall, at a minimum, maintain the structural integrity of the basin during a 25-year storm of 24-hour duration; runoff coefficients used in runoff calculations shall correspond to a bare earth condition or those conditions expected to exist while the sediment basin is utilized. Sediment Trapping Devises - Answers 1. place near the lowest drainage points of a project 2. install as a first-step measure [MS-4] 3. stabilize immediately [MS-5] 4. must include outlet protection for basins [MS-11] Minimum Standard 7 - Answers Cut and Fill Slopes roughening the surface of the slope decreases runoff, lowers the velocity runoff, increases water retention, and leads to better seed germination slopes that are found to be eroding excessively within on year of permanent stabilization shall be provided with additional slop stabilizing measures until the problem is corrected Minimum Standard 8 - Answers Concentrated Runoff shall not flow down cut or fill slopes unless contained within an adequate temporary or permanent channel, flume or slope drain structure outlets of these drains need outlet protection to prevent erosion from the concentrated flow size of pipe depends on drainage area temporarily conduct concentrated stormwater runoff safely down the face of a cut or fill slope without causing erosion on or below the slope Minimum Standard 9 - Answers Water Seeps whenever water seeps from a slope face, adequate drainage or other protection shall be provided cut and fill operations may expose shallow aquifers or groundwater tables from which water may seep through the side of a slope Minimum Standard 10 - Answers Inlet Protection all storm sewer inlets that are made operable during construction shall be protected so that sediment-laden water cannot enter the conveyance system without first being filtered or otherwise treated to remove sediment storm sewers are designed to efficiently transport stormwater away from the site, so when sediment enters the storm sewer system, two negative effects can occur: 1. when velocity of flow is high, much of the sediment will be quickly transported to the nearest receiving channel 2. when velocity of the flow is low, the sediment may be deposited in the pipes resulting in clogging and potential flooding of a site during storm events prevents sediment from entering storm drainage systems prior to permanent stabilization of the disturbed area Silt Fence Drop Inlet Protection vs. Block and Gravel Drop Inlet Sediment Filter - Answe

Vista previa del contenido

Erosion and Sediment Control Exam Questions and Correct Answers Latest Update 2024 ( Already
Passed)



Minimum Standard 1 - Answers Stabilization



permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final
grade is reached on any portion of the site; temporary soil stabilization shall be applied within seven
days to denuded areas that may not be at final grade but will remain dormant for longer than 14 days;
permanent stabilization shall be applied to areas that are to be left dormant for more than one year

Site NOT at Final Grade - Answers - stabilize in 14 days

- temporarily seed

- mulch

- permanently stabilize if dormant > 1 year

Site at Final Grade - Answers - stabilize in 7 days (recommended immediately)

- permanently or temporarily seed and mulch

- mulch/matting/straw

Minimum Standard 2 - Answers Stock Piles, Waste and Borrow Areas



during construction, soil stock piles and borrow areas shall be stabilized or protected with sediment
trapping measures



mulch prevents erosion by protecting the surface from raindrop impact and silt fence intercepts and
detains from disturbed areas

Minimum Standard 3 - Answers Permanent Vegetation



permanent vegetation cover shall be established on denuded areas not otherwise permanently
stabilized (permanent vegetation shall not be considered established until a ground cover is achieved
that is uniform, mature enough to survive, and will inhibit erosion *there is no % associated with this*)

,reduce erosion and decrease sediment yield from disturbed area



this is the standard used to verify that a site is ready for release of bonds or surety

Minimum Standard 4 - Answers First-Step Measures



Sediment basins and traps, perimeter dikes, sediment barriers and other measures intended to trap
sediment shall be constructed as a first step in any land-disturbing activity and shall be made functional
before upslope land disturbance takes place



a certain amount of initial land disturbance may be required to provide access for equipment to install
the perimeter controls, but site clearing and grading should be kept to a minimum until the perimeter
controls are in place



intercepts and detains small amounts of sediment from disturbed areas during construction operation
to prevent sediment from leaving the site and decrease velocity of sheet flows and low-to-moderate
level channel flow

Perimeter Controls - Answers assures that sediment does not leave the perimeter of the land-disturbing
area once site clearing, grading, and construction commences



Examples: silt fences, sediment traps, sediment basins, construction entrance, temporary diversions,
diversions

Minimum Standard 5 - Answers Earthen Structure Stabilization



stabilization measures shall be applied to earthen structures such as dams, dikes, and diversions
immediately after installation



reduce erosion and sedimentation and reduce damage from sediment and runoff to downstream or off-
site areas

Minimum Standard 6 - Answers Traps and Basins

, sediment traps and basins shall be designed and constructed based upon the total drainage area (not
just disturbed area) to be served by the trap or basin

Sediment Traps - Answers minimum storage capacity shall be 134 cubic yards per acre of drainage area
and shall only control drainage areas less than 3 acres



*stone outlet = trap*

Sediment Basins - Answers surface runoff from disturbed areas that is comprised of flow from drainage
areas greater than or equal to 3 acres shall be controlled by a basin; minimum storage capacity of a
sediment basin shall be 134 cubic yards per acre of drainage area; the outfall system shall, at a
minimum, maintain the structural integrity of the basin during a 25-year storm of 24-hour duration;
runoff coefficients used in runoff calculations shall correspond to a bare earth condition or those
conditions expected to exist while the sediment basin is utilized.

Sediment Trapping Devises - Answers 1. place near the lowest drainage points of a project



2. install as a first-step measure [MS-4]



3. stabilize immediately [MS-5]



4. must include outlet protection for basins [MS-11]

Minimum Standard 7 - Answers Cut and Fill Slopes



roughening the surface of the slope decreases runoff, lowers the velocity runoff, increases water
retention, and leads to better seed germination



slopes that are found to be eroding excessively within on year of permanent stabilization shall be
provided with additional slop stabilizing measures until the problem is corrected

Minimum Standard 8 - Answers Concentrated Runoff

Información del documento

Subido en
11 de diciembre de 2024
Número de páginas
21
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$8.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TutorJosh
3.5
(77)
Vendido
508
Seguidores
16
Artículos
33102
Última venta
1 semana hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes