Demand - answer-is defined as a need for a particular product or component. This demand could come
from any number of sources.
Demand management - answer-is the function of recognizing all demands for goods and services to
support the marketplace
Order processing - answer-is the activity required to administratively process a customer's order and
make it ready for shipment or production, this may involve producing and forwarding a sales order to
the most efficient supply channel such as an inventory storage location authorizing the goods to be
shipped or production plant authorizing production and specifying all information required by the
master planner
Influencing demand - answer-describes the activities of product and brand management marketing and
sales to convince customers to purchase the organizations products and services so that the
organization's business objectives are met or exceeded
Pdca model - answer-is defined as the plan do check action model for quality improvement
Planning demand (fixed high-capacity strength) - answer-this organizational strategy involves meeting
the man to the maximum extent possible by providing the necessary capacity to meet peak demand at
any time
Communicating demand ( highly variable capacity strategy) - answer-this organizational strategy
involves matching supply to demand as closely as possible by being flexible enough to increase or
reduce capacity spontaneously as the man changes
Influencing demand (moderately variable capacity strategy) - answer-this organizational strategy
involves leveling production and carefully managing the man to meet optimal capacity, the focus is on
influencing the man so that there is little need to change capacity sometimes this is called demand
shaping
Managing and prioritizing demand (fixed average capacity strategy) - answer-this organizational strategy
involves controlling the man to the maximum extent possible through scheduling promotions cues and
rationing, the focus is on managing and prioritizing the man because fixed average capacity will by
definition result in periods of insufficient supply
Collaborative planning forecasting and replenishment (cpfr) - answer-it is a collaboration process
whereby supply chain trading partners can jointly plan key supply chain activities from production and
delivery of raw materials to production delivery of final products to end customers. It is a process
philosophy for facilitating collaborative communications
Distributor integration (di) - answer-this occurs when distributors are integrated using information
systems so the expertise and inventory located at one distributor are available to the others such as
,sometimes exists between auto dealerships. Each distributor can check the inventories of other
distributors to locate a needed product or part. An obstacle to ownership of inventory
Quick response program (qrp) - answer-this is a system of linking file retail sales with production and
shipping schedules back through this chain of supply. This employees point-of-sale scanning and
electronic data interchange in may use direct ship meant from a factory to a retailer. The supplier uses
the point of sale data as the basis for scheduling production in determining inventory levels to improve
synchronization with actual demand. This can result in a reduction of lead times
Continuous replenishment (cr) - answer-is a process by which a supplier is notified daily of actual sales
or warehouse shipments and commits to replenishing the sales without stock-outs and without
receiving replenishment orders, the result is a lowering of associated costs an improvement in inventory
turnover.
Vendor managed inventory (vmi) - answer-the vendor through mutual agreement has access to the
customer's point of sale inventory data for items they supply. The vendor is responsible for maintaining
the inventory level required by the customer and performs actual resupply. Procter & gamble for
example took over management of the inventory of procter & gamble diapers at wal-mart to straighten
out the bulwhip effect in their supply chain
Mixed forecast - answer-is a forecast of the proportion of products that will be sold within a given
product family or the proportion of options offered with in a product line, even though the appropriate
level of unit is forecasted for a given product line and inaccurate mix forecast in create material
shortages and inventory problems
A trend - answer-is the general upward or downward movement of a variable over time the two
examples being linear and exponential
Cycles - answer-are periodic upward neutral or downward shifts in demand lasting longer than one year
Seasonality - answer-is a predictable repetitive pattern of the measured within a year where demand
grows and declines. These patterns are calendar related
Random variation - answer-is a fluctuation data that is caused by uncertain or random occurrences
Qualitative methods - answer-rely on judgement rather than math, these methods black scientific
precision but can be used on their own in vault all situations or when there are no historical data
available such as for a new product. Judgemental expert forecasting and the delphi method
Simple moving average - answer-is the average of the man from several preceding periods. Three and
six-month periods are commonly used
Weighted moving average - answer-is a forecasting method that place is weights on the periods being
average usually to put greater emphasis on the more recent periods and relatively less emphasis on the
more distant.
Correlation - answer-is an observation that the change and an independent variable has a measurable
effect on a dependent variable. However just because the effect can be reliably observed over time does
, not mean that the one thing cause the other thing it could be that some 3rd force is affecting both of
them or the correlation could be a coincidence that would be proven incorrect after a longer period of
study
Leading indicator - answer-is a specific business activity index that indicates future trends this provides
information that enables organizations to anticipate or predict micro or macro economic changes in the
future. One example would be building permits issued for new production facilities housing warehouses
and utilities, business building permits imply future construction
Lagging indicator - answer-are the economic and financial factors that reflect the changes that have
already occurred in the economy. They usually confirm a pattern and often provide data or actual
information about 6 months after the fact and therefore are more reactionary. One of the most widely
used lagging indicators is the unemployment rate
Simple regression also called linear regression - answer-uses a formula to make an association between
a dependent variable y and the independent variable x the other two elements are alpha and beta. Beta
is the slope which is a value used as a multiplier to find the correct placement of the forecast result.
Alpha is the intercept which is where the slope intercept 0 on a chart
y = alpha + beta (x)
Coefficient of correlation - answer-statistical term that defines the strength of correlation. Number
between negative one and positive one where -1 is a perfect negative correlation and positive one is a
perfect positive correlation
Multiple regression - answer-an extension of simple regression, there are multiple predictive variables
rather than just one
Forecast error - answer-is the difference between actual demand and forecast demand stated as an
absolute value or as a percentage
Bias - answer-is a consistent deviation from the mean in one direction.
it exists when the cumulative actual demand differs from the cumulative actual forecast
Mean absolute deviation (mad) - answer-is the average of the absolute values of the deviations of
observed values from some expected value
Tracking signal - answer-is the ratio of the cumulative algebraic sum of the deviations between the
forecast and the actual values to the mean absolute deviation
Time fence - answer-is a policy or guideline established to note where various restrictions or changes in
operating procedures take place. A time fence marks off a zone in which otherwise available product
may not be promised to deliver it without permission
Frozen zone capacity - answer-materials are committed to specific orders orders are there for frozen
inside the fence any changes require the approval of senior management