IPC A 610 Exam Study Guide with
Complete Solutions
Class 1 Product - Answer✔✔-General Electronics Product - includes products where the major
requirement is function of the completed assembly.
Class 2 Product - Answer✔✔-Dedicated Service Electronic Product - Continued performance and
extended life required. Uninterrupted service is desired but not required.
Class 3 Product - Answer✔✔-High Performance Electrical Product - Continued high performance or
performance-on-demand is critical. Equipment downtime cannot be tolerated. Equipment might be used
for life-support or other critical systems.
Who as the ultimate responsibility for identifying the class to which the assembly is evaluated? -
Answer✔✔-The Customer.
Shall - Answer✔✔-Invokes a requirement for manufacturers of all classes or product, and failure to
comply with the requirement is a noncompliance to this standard.
Order of Precedence in event of conflict 1 - Answer✔✔-1. Procurement as agreed and documented
between customer and supplier.
Order of Precedence in event of conflict 2 - Answer✔✔-Master drawing or master ass. drawing reflecting
the customer's detailed requirements.
Order of Precedence in event of conflict 3 - Answer✔✔-IPC-1-610 when invoked by the customer or
contract.
Page 1/6
, EMILLECT 2024/2025 ACADEMIC YEAR ©2024 EMILLECT. ALL RIGHTS RESERVED. FIRST PUBLISH OCTOBER 2024.
If documents other than IPC-A-610 are cited, the order of precedence shall be defined in the _ -
Answer✔✔-Procurement documents
Target Condition - Answer✔✔-A condition that is close to perfect, but is not always achievable and may
not be necessary to ensure the reliability of the assembly.
Acceptable Condition - Answer✔✔-A condition that, while not necessarily perfect, will maintain integrity
and reliability of the assembly
Defect Condition - Answer✔✔-The form, fit or function of the assembly is inadequate for use in its end
use environment.
A defect for Class 1... - Answer✔✔-automatically implies a defect for Class 2 and 3. A defect for Class 2
implies a defect for Class 3.
Disposition - Answer✔✔-The determination of how defects should be treated. These include rework, use
as is, scrap, and repair.
Who dispositions defect conditions? - Answer✔✔-The manufacturer, based on design, service and
customer requirements.
Process Indicator Conditions - Answer✔✔-A condition (not a defect) that does not affect the form, fit or
function of a product.
Process indicators should be... - Answer✔✔-monitored as part of the process control system
Is disposition of individual process indicators required? - Answer✔✔-No, and affected products should
be used as-is.