Essentials
What is the definition of a critical path? - answer-The longest sequence of activities
in a project plan.
You determine that a project's optimistic completion time is 12 days; the worst case
scenario is 42 days, and its most probable time is 30 days.
What is the expected project completion time? - answer-29 days
This is the correct option. In the PERT formula, the standard default for estimating
duration is to weigh most probable time four times higher than the optimistic or
pessimistic times. The calculation would therefore be (12 + 4(30) + 42) / 6, which
equals 29 days.
E = (O + 4M + P) / 6. The calculation would therefore be (12 + 4(30) + 42) / 6,
How do you estimate the duration of a project? - answer-With the PERT formula.
(Optimistic time) + 4(Most probable time) + (Worst-case time) /6
E= (O+4M+P)/6
Match each characteristic to the most appropriate documentation category.
Categories may have more than one match.
Budget reviews
Customer audits
Status reports
Management reviews - answer-Budget reviews - Check cost performance and
resource utilization.
Customer audits - Document project is meeting contractual obligations.
Status reports - Outline the project's health. Document actual versus planned
performance.
Management reviews - Show the organizational perspective. Are conducted by
senior management.
Which project activities are associated with risk analysis? - answer-Determining
probability of risk occurrence.
Determining measures to prevent risk.
Balancing the impact of risk with the cost of prevention.
Identifying and assessing risk factors.
Identifying the assets to be protected.
You're working on a Six Sigma project to improve the production process at a
company that makes optical lenses.
Match each project charter key element to the question it answers.
Business case
Goal statement
Key deliverable
Problem statement
, Project scope - answer-Business case - "Why should we do this project?"
Goal statement - "What results do we expect and how will they be measured?"
Key deliverable - "When will each main activity take place?"
Problem statement - "What is the impact of the issue we're trying to fix and how is it
measured?"
Project scope - "What processes are we addressing and at what level?"
You're working to improve an online bookseller's delivery process. The three-day
delivery promise is, in many cases, not being met.
What is the best problem statement for this project? - answer-"On-time deliveries of
books ordered from our web site are averaging 60% as measured from shipping
documents. Canceled orders and refused shipments have resulted in a loss of
$120,000 in the past six months."
Which statement could be an example from the business case section of a project
charter? - answer-"Automation of the production line will increase productivity and
reduce defects from human error. The estimated ROI over three years is 225%."
What does the problem statement section describe for a project charter? - answer-A
successful problem statement describes the problem to be solved and the impact of
that problem on the business.
What does the business case section describe for a project charter? - answer-The
business case describes both the rationale for the project and its value to the
organization.
What are good scoping practices for a Six Sigma project? - answer-Prevent the
project from crossing boundaries.
Set clear expectations.
Write a concise and precise scope statement.
Determine which other projects impact your project.
Be conscious of time and money.
Sequence the steps of creating and using a Pareto chart. - answer-1. List the causes
in descending order.
2. Calculate cumulative percentages.
3. Build the chart.
4. Plot the cumulative frequency of defects.
5. Identify the vital few causes of error.
You're working on a project to improve the process for scheduling security staff at a
shopping mall.
Classify each metric as either primary or secondary. Metric categories may have
more than one match.
Primary
Secondary - answer-Primary
The number of customers visiting the mall.
The number of security guards on staff.