Basics
What are the correct interpretations of this Gantt chart? - answer--The chart shows
no flexibility in the path beginning with task A
-Tasks E, F, and G are predecessors of task H
-There are ten tasks represented on the chart
How is a work breakdown structure used to plan and monitor a Six Sigma project? -
answer-It can help define team members' responsibilities
What are some best practices for scoping a Six Sigma project? - answer--Write a
concise and precise scope statement
-Prevent the project from crossing boundaries
-Be time conscious
What activities are required to prepare for and conduct a tollgate review? - answer--
Prepare an agenda for the meeting so that participants understand the phase under
review
-Invite team members and stakeholders who will present information and be
responsible for signing off the phase
What are the best practices for creating tree diagrams? - answer--Training the
leader of the exercise on how the process of creating a tree diagram works
-Not allowing groups or levels to merge
-Defining the process for breaking down details at the start
-Using no more than four items at any level
1.Defines the quality and results that the team expects to achieve
2.Estimates output completion data so the team can judge if it's on track
3.Sets the boundaries of the project and provides a baseline for project
expectations and requirements
4.Sets forth the value and rationale of the project - answer-1.Goal statement
2.Key deliverables
3.Project scope
4.Business case
Which purposes are matrix diagrams used for? - answer--Determining causes and
effects of issues
-Showing the potential of improvement efforts during the Improve stage
-Combining two tree diagrams into a single matrix
-Assigning project tasks
1.Contact publishers a day before the deadline to remind them to sign the contract
between their journal and your company
2.Communicate with the executive director of a major Internet provider to gauge
her interest in partnering in the project