WGU BUSUNESS 722 FINAL ASSESSMENT TEST SOLUTIONS FOR FALL SESSION EXAM. Status: Passed 1. A firm begins its strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business management project. Which aspect of project management applies to this firm’s project? YOUR ANSWER CORRECT ANSWER Independent operations Interdependent tasks Regulatory concept External environment 2. A firm begins its strategic business initiative of developing a new business model to enhance its competitiveness. What can be identified as a strategic business initiative for this firm? YOUR ANSWER CORRECT ANSWER Timely payment of liabilities Liaison with regulatory agencies Improvement in product design Environmental scanning 3. A firm begins a strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. Which stakeholder would have triggered this strategic business initiative? YOUR ANSWER CORRECT ANSWER Director of operations Accessibility Policy Accessibility Settings Production supervisor Project sponsor Financial controller 4. Which group is included in the five process groups? YOUR ANSWER CORRECT ANSWER Risk process group Closing process group Communication process group Quality process group 5. What does PRINCE2 stand for? YOUR ANSWER CORRECT ANSWER PRoject INsights for CompEtitiveness PRojects IN a Competitive Environment PRoject INsights and CompEtencies PRojects IN a Controlled Environment 6. Which PMBOK process group is described as the delivery part of project management where the main activity happens? YOUR ANSWER CORRECT ANSWER Planning Executing Controlling Closing 7. Which advantage does the functional (departmentalized) organizational structure provide for a firm with multiple projects? YOUR ANSWER CORRECT ANSWER Lines of authority are clear. The project customer is the only focus. It is efficient for collaboration and cooperation between departments. Each project is managed holistically. 8. Which two organizations are examples of organizations with the functional organizational structure? Choose 2 answers YOUR ANSWER CORRECT ANSWER Microsoft The U.S. Department of State The U.S. National Aeronautics and Space Administration (NASA) The U.S Department of Energy Google Inc. 9. An organization expects to use a project management office (PMO) to support multiple projects that will be implemented within a projectized organizational structure. Which implied effect is a benefit to this organization? YOUR ANSWER CORRECT ANSWER Project team members retain their functional responsibilities. Project team members become full-time employees. Project team members gain access to the newest technologies and skill sets. Project team members gain access to historical data from other projects. 10. Regardless of the organizational structure used to manage a project, an organization elects to use a project management office (PMO). Which benefit will this organization gain? YOUR ANSWER CORRECT ANSWER Projects will coordinate resource usage by monitoring the status of shared resources. Projects will define the organization’s corporate strategy in the project charter. Projects will receive a 10% managerial reserve fund to cover warranty back charges. Projects will eliminate the costs incurred from having to follow corporate procedures. 11. During a certain project phase, specific blueprints are drawn and approved, materials and labor costs are estimated, prototypes are created, and work activities and tasks are identified. Also, quality expectations, measurements, and costs are defined. During which project phase do these activities occur? YOUR ANSWER CORRECT ANSWER Defining Planning Executing Closing 12. Place the project activities in order of occurrence from first (1) to last (5). Select your answer from the pull-down list. YOUR ANSWER CORRECT ANSWER Developing the work 2 2 breakdown structure Capturing lessons learned 5 5 Working to produce project deliverables 3 3 Collecting customer 1 1 requirements Customers evaluating the 4 4 project outcomes 13. During which life cycle phase is the vast majority of the actual work to produce the project’s deliverables completed? YOUR ANSWER CORRECT ANSWER Defining

Vista previa del contenido

WGU BUSUNESS 722 FINAL ASSESSMENT TEST
SOLUTIONS FOR 2024-2025 FALL SESSION EXAM.
Status: Passed

1. A firm begins its strategic business initiative of developing a new business model that will allow the
firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a
business management project.

Which aspect of project management applies to this firm’s project?
YOUR CORRECT
ANSWER ANSWER


Independent operations


Interdependent tasks


Regulatory concept


External environment


2. A firm begins its strategic business initiative of developing a new business model to enhance its
competitiveness.

What can be identified as a strategic business initiative for this firm?
YOUR CORRECT
ANSWER ANSWER


Timely payment of liabilities


Liaison with regulatory agencies


Improvement in product design


Environmental scanning


3. A firm begins a strategic business initiative of developing a new business model that will allow the
firm to deliver an efficient, tailored service to its customers.

Which stakeholder would have triggered this strategic business initiative?
YOUR CORRECT
ANSWER ANSWER


Director of operations
Accessibility Policy Accessibility Settings

, YOUR CORRECT
ANSWER ANSWER


Production supervisor


Project sponsor


Financial controller


4. Which group is included in the five process groups?
YOUR CORRECT
ANSWER ANSWER


Risk process group


Closing process group


Communication process group


Quality process group


5. What does PRINCE2 stand for?
YOUR CORRECT
ANSWER ANSWER


PRoject INsights for CompEtitiveness


PRojects IN a Competitive Environment


PRoject INsights and CompEtencies


PRojects IN a Controlled Environment


6. Which PMBOK process group is described as the delivery part of project management where the
main activity happens?
YOUR CORRECT
ANSWER ANSWER


Planning


Executing


Controlling


Closing


Accessibility Policy Accessibility Settings

, 7. Which advantage does the functional (departmentalized) organizational structure provide for a firm
with multiple projects?
YOUR CORRECT
ANSWER ANSWER


Lines of authority are clear.


The project customer is the only focus.


It is efficient for collaboration and cooperation between
departments.


Each project is managed holistically.


8. Which two organizations are examples of organizations with the functional organizational
structure?

Choose 2 answers

YOUR CORRECT
ANSWER ANSWER


Microsoft


The U.S. Department of State


The U.S. National Aeronautics and Space Administration (NASA)


The U.S Department of Energy


Google Inc.


9. An organization expects to use a project management office (PMO) to support multiple projects that
will be implemented within a projectized organizational structure.

Which implied effect is a benefit to this organization?
YOUR CORRECT
ANSWER ANSWER


Project team members retain their functional responsibilities.


Project team members become full-time employees.


Project team members gain access to the newest technologies and
skill sets.


Accessibility Policy Accessibility Settings

Información del documento

Subido en
28 de septiembre de 2024
Número de páginas
29
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas
$13.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Nurslink
3.5
(27)
Vendido
237
Seguidores
72
Artículos
1714
Última venta
16 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes