Project Controls - Answer Proactive method to ensure meeting project constraints
What does project controls answer? - Answer where are we now and where are we
going
Projects over budget at only XX% complete usually overrun at completion - Answer 15%
Importance of project controls - Answer take action early to stop the bleeding
Ways to define project success - Answer financial performance, process adherence and
operational performance, project team and customer satisfaction
Additional measures of project performance - Answer compliance w/ contract, H and S,
delivered quality, good risk management, baseline progress, corrective actions
What is a KPI - Answer Key Performance Indicators
SMART metrics - Answer specific, measurable, actionable, relevant, timely
Financial KPI components - Answer technical completion of scope, measurement of
performance agnst budget and schedule
When to monitor? - Answer design - monthly, construction - major milestones
Tricks to watch out for - Answer 'rubber baselines' (changing the baseline w/o change
control), omitting their milestones, contractor constraints (front loading, excusing slips)
What is EAC - Answer Estimate at Complete: est of project costs or price at end of
project
Estimate to Complete (ETC) - Answer future costs (part of EAC)
Formula for EAC - Answer = PJTD Direct + Future Costs
What is the forecast variance at completion? - Answer cost budget - EAC
What is %spent? - Answer = PJTD Cost/Cost Budget
7 Methods for statusing - Answer milestones with weighted values, fixed formula, %
complete estimate, % complete w/ milestone 'gates', equivalent completed units, LOE
(level of effort), %complete (BEST way)
Milestones w/ weight values - Answer % complete additive w/ each milestone,
COMPLETE SOLUTION
Project Controls - Answer Proactive method to ensure meeting project constraints
What does project controls answer? - Answer where are we now and where are we
going
Projects over budget at only XX% complete usually overrun at completion - Answer 15%
Importance of project controls - Answer take action early to stop the bleeding
Ways to define project success - Answer financial performance, process adherence and
operational performance, project team and customer satisfaction
Additional measures of project performance - Answer compliance w/ contract, H and S,
delivered quality, good risk management, baseline progress, corrective actions
What is a KPI - Answer Key Performance Indicators
SMART metrics - Answer specific, measurable, actionable, relevant, timely
Financial KPI components - Answer technical completion of scope, measurement of
performance agnst budget and schedule
When to monitor? - Answer design - monthly, construction - major milestones
Tricks to watch out for - Answer 'rubber baselines' (changing the baseline w/o change
control), omitting their milestones, contractor constraints (front loading, excusing slips)
What is EAC - Answer Estimate at Complete: est of project costs or price at end of
project
Estimate to Complete (ETC) - Answer future costs (part of EAC)
Formula for EAC - Answer = PJTD Direct + Future Costs
What is the forecast variance at completion? - Answer cost budget - EAC
What is %spent? - Answer = PJTD Cost/Cost Budget
7 Methods for statusing - Answer milestones with weighted values, fixed formula, %
complete estimate, % complete w/ milestone 'gates', equivalent completed units, LOE
(level of effort), %complete (BEST way)