Construction Quality Management for Contractors
The _________ consists of daily checks of the work to assure continuing compliance
with contract requirements - Correct Answer Follow-up Phase
Design-Build contracts require - Correct Answer the QC Manager to be in place and
take an active role in the review and coordination of the design.
Which of the following is included in all three phases of the Three Phases of Control? -
Correct Answer Safety
The purpose of Construction Quality Management is to - Correct Answer Achieve the
quality established by properly developed requirements through the combined
responsibility, but separate, efforts of contractors and government personnel
Testing is extremely important in construction quality management and is performed by
- Correct Answer Both the contractor and the government
The primary purpose of the Three-Phase Control System is to - Correct Answer Require
the contractor to plan, schedule, and perform quality management actions to assure
work meets all specified quality standards
Quality Assurance Personnel have the responsibility to - Correct Answer Require the
contractor to maintain the quality specified in the plans and specifications
The _________________ is the appropriate time to assure that all materials and/or
equipment have been tested, submitted, and approved - Correct Answer Preparatory
Phase
, The Preconstruction Conference and Coordination and Mutual Understanding Meeting
Are - Correct Answer Conducted prior to the commencement of any physical
construction work
Contractor testing procedures: - Correct Answer Are specified in the technical specs,
outlined in the QCP, and addressed at Coordination and Mutual Understanding Meeting
The Quality Control Plan contains - Correct Answer Identification of individual quality
control personnel, including name, qualifications, assigned duties, responsibilities and
authorities.
Tests that are unannounced, randomly performed, and repeat quality control tests are -
Correct Answer Quality assurance tests
The contractor is required to conduct a Preparatory Phase Meeting before they begin
any definable feature of work except when - Correct Answer There are no exceptions to
the rule
During the punch-out inspection of a project: - Correct Answer Quality Control personnel
prepare and punch-list and make corrections
The Quality Control Report should include - Correct Answer All of the above
In a design build contract, if the contractor has a question about the design, what is the
process to get an answer? - Correct Answer Contractor submits a design verification
request to the contractor's design team
Submittals are - Correct Answer Necessary to demonstrate that the proposed materials,
etc. are in compliance with the contract.
The _________ consists of daily checks of the work to assure continuing compliance
with contract requirements - Correct Answer Follow-up Phase
Design-Build contracts require - Correct Answer the QC Manager to be in place and
take an active role in the review and coordination of the design.
Which of the following is included in all three phases of the Three Phases of Control? -
Correct Answer Safety
The purpose of Construction Quality Management is to - Correct Answer Achieve the
quality established by properly developed requirements through the combined
responsibility, but separate, efforts of contractors and government personnel
Testing is extremely important in construction quality management and is performed by
- Correct Answer Both the contractor and the government
The primary purpose of the Three-Phase Control System is to - Correct Answer Require
the contractor to plan, schedule, and perform quality management actions to assure
work meets all specified quality standards
Quality Assurance Personnel have the responsibility to - Correct Answer Require the
contractor to maintain the quality specified in the plans and specifications
The _________________ is the appropriate time to assure that all materials and/or
equipment have been tested, submitted, and approved - Correct Answer Preparatory
Phase
, The Preconstruction Conference and Coordination and Mutual Understanding Meeting
Are - Correct Answer Conducted prior to the commencement of any physical
construction work
Contractor testing procedures: - Correct Answer Are specified in the technical specs,
outlined in the QCP, and addressed at Coordination and Mutual Understanding Meeting
The Quality Control Plan contains - Correct Answer Identification of individual quality
control personnel, including name, qualifications, assigned duties, responsibilities and
authorities.
Tests that are unannounced, randomly performed, and repeat quality control tests are -
Correct Answer Quality assurance tests
The contractor is required to conduct a Preparatory Phase Meeting before they begin
any definable feature of work except when - Correct Answer There are no exceptions to
the rule
During the punch-out inspection of a project: - Correct Answer Quality Control personnel
prepare and punch-list and make corrections
The Quality Control Report should include - Correct Answer All of the above
In a design build contract, if the contractor has a question about the design, what is the
process to get an answer? - Correct Answer Contractor submits a design verification
request to the contractor's design team
Submittals are - Correct Answer Necessary to demonstrate that the proposed materials,
etc. are in compliance with the contract.