CEPSCI PRACTICE TEST
1972 clean water act - ANS-Administered by the US environmental protection agency
(EPA) Created the NPDES

1987 - ANS-Amendment to CWA CALLED WATER QUALITY ACT

NPDES in south carolina - ANS-South Carolina is NPDES delegated state.

NPDES regulations are administered by - ANS-SCDHEC

CGP authorizes - ANS-stormwater discharges from construction sites

Who must obtain NPDES coverage - ANS-land disturbing activities greater than or
equal to 1 acre
-land disturbance less than 1 ac within 1/2 miles of water body in SC costal zone

NPDES permits are issued to - ANS-operator-person or company for a particular
discharge

primary permittee - ANS--has day to day operational control to ensure compliance with
SWPP
-typically the owner or developer

primary permittee responsibilites - ANS-submit NOI, Preparation of the C_SWPPP

Secondary permittee - ANS-individual lot owner or residential builder that conducts land
disturbing activity limited to an individual lot or group of lots as part of approved LCP of
development

contractors - ANS-must on Contractor Certification- D-0437

On-Site SWPPP - ANS-SCDHEC CGP, NOI, NPDES coverage approval letter,
Contractor Certifications, Local Approvals, USACE approvals, Critical area
permit(coast)

OS_SWPPP - ANS-a copy of signed and certified SWPPP, NOI, and CGP coverage
letter from DHEC must be retained at site or electronically accessible

, minor modification to ON-SWPPP - ANS-minor modifications made directly in the
field,do not need approval by DHEC- additional BMP's, removal of disturbed areas

major modifications to OS-SWPPP - ANS-must be made by qualified individual and
submitted to DHEC or appropriate delegated entity for approval

Phased plan requirement > 5 - ANS-include a phased stormwater management plan
which identifies all BMP's and grading work conducted during a specific portion of the
sites construction sequence. Each phase identified on at least one separate plan sheet.

Phased plan requirement < 10 but > 5 acres - ANS-at least two separate plan phases
are required - initial land disturbance phase - stabilization phase

Phased plan requirement ≥ 10 acres - ANS-at least 3 separate plan phases are required
- initial land disturbance phase - construction phase - stabilization phase

All compliance inspection must include invesg. of, at a minimum of 5 of the following -
ANS-1. areas of site disturbed by construction activity and areas used for storage of
materials exposed to precipitation
2. stormwater conveyance systems for evidence of sediment
3. BMP's identified in OS-SWPPP
4. Discharge location to investigate if sediment leaving site, or if such locations are
inaccessible, nearby downstream location if possible.
5. Where vehicles enter or exit site for evidence of off-site sediment tracking.

inspection frequency after construction begins - ANS-at least once a week or within 24
hours of end of storm event >0.5 inches

Inspection frequency for sites that have reached temporary stablization - ANS-Once
every month

Linear site inspection - ANS-linear activites may limit access to disturbed areas, in such
cases representative inspections may be performed

representative inspections (linear site inspection) - ANS-personnel must investigate
BMP's along the site for 0.25 miles above and below each access point where the site
intersects with -roadway - undisturbed right of way - other similar feature- Condition
along each inspected segment are considered "respresentative" along that reach of
construction

Información del documento

Estudio
Subido en
16 de junio de 2024
Número de páginas
12
Escrito en
2023/2024
Tipo
Examen
Contiene
Preguntas y respuestas
$8.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Ace360PRO
4.7
(108)
Vendido
262
Seguidores
3
Artículos
10566
Última venta
1 mes hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes