CHFM EXAM 2024 WITH 100% CORRECT ANSWERS A project estimator is developing a cost estimate for construction of a new diagnostic imaging wing. The projected costs are: Fixed equipment installation charges $700,000 Site isolation $50,000 Annual utilities $425,000 Construction materials $1,200,000 Portable equipment $900,000 Annual depreciation $275,000 What are the expected contractor expenses? - correct answer 1,600,000 Which of the following contribute to typical general contractor fees: 1. Permit and inspection fees 2. General conditions 3. Overhead and profit