Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 1 fuera de 3 páginas
Examen

Virginia Exam Advanced Questions & Answers (GRADED A+)

Document preview thumbnail
Vista previa 1 fuera de 3 páginas

What is the name of the process when a facilitator meets with the major participants in a project, prior to the commencement of the project, to identify the shared goals of all participants? - ANSWER-Partnering. A cost plus contract calls for the contractor to receive direct costs for labor and materials, and a markup of 20% of direct costs. The contractor is also to receive a bonus of 15% of savings if total cost to the owner is less than $80,000, and a bonus of $1,000 per day if the project is completed early. Final costs for direct labor and materials are $60,000. The project is completed 3 days early. What is the total amount due the contractor? - ANSWER-Between $75,001 and $80,000. The owner requests for changes which will cost the contractor $15,000 in labor and materials and $2,250 in overhead costs. With the change, the contractor would be relieved of $18,000 in labor and materials costs, and $2,400 in overhead costs from the original contract. The original bid included profit of 20% of all costs. The contractor wants to make a profit of 20% of all costs on the changes. The adjusted contract price for the change order should be - ANSWER-a decrease of $3,780. A lump sum contract on a project has a total contract price of $160,000. Retainage has been held back at 10%. The contractor has received progress payments for 75% of the project. The contractor submits a request for final payment for the now completed project. The final payment amount should be for - ANSWER-more than $50,000. A permit is obtained on Friday, May 1. The materials are to be delivered May 8. The materials are needed when labor begins on May 11. It is estimated that 15 days of labor are REQUIRED. The crew will work every day, including weekends and holidays. The project is scheduled to be completed on June 8. How many float days are available for the labor for this project? - ANSWER-13 Which of the following would typically be covered by a contractor's comprehensive general liability insurance policy? - ANSWER-Damage to adjoining property from a crane accident. A contractor puts in a claim under a comprehensive standard general liability policy. The policy has no additional coverage, riders, or floaters, and has a $500 deductible per occurrence. The claim is for a job-site accident that caused $2,000 of injuries to employees, $1,800 of injuries to a pedestrian, $2,300 damage to the contractor's equipment, and $1,750 loss of project materials purchased by the contractor. The insurance company is liable for - ANSWER-$1,300.

Vista previa del contenido

Virginia Exam Advanced Questions &
Answers (GRADED A+)

In the previous year, a company had revenues of $500,000, project overhead of
$40,000 and company overhead of $75,000. The company expects the percentage
for project and company overhead to remain the same for the current year. The
company desires to make a 10% profit on a project it is bidding. The project would
have $80,000 in direct costs. What should the bid price be? - ANSWER-Between
$110,000 and $120,000.

What is the name of the process when a facilitator meets with the major participants
in a project, prior to the commencement of the project, to identify the shared goals of
all participants? - ANSWER-Partnering.

A cost plus contract calls for the contractor to receive direct costs for labor and
materials, and a markup of 20% of direct costs. The contractor is also to receive a
bonus of 15% of savings if total cost to the owner is less than $80,000, and a bonus
of $1,000 per day if the project is completed early. Final costs for direct labor and
materials are $60,000. The project is completed 3 days early. What is the total
amount due the contractor? - ANSWER-Between $75,001 and $80,000.

The owner requests for changes which will cost the contractor $15,000 in labor and
materials and $2,250 in overhead costs. With the change, the contractor would be
relieved of $18,000 in labor and materials costs, and $2,400 in overhead costs from
the original contract. The original bid included profit of 20% of all costs. The
contractor wants to make a profit of 20% of all costs on the changes. The adjusted
contract price for the change order should be - ANSWER-a decrease of $3,780.

A lump sum contract on a project has a total contract price of $160,000. Retainage
has been held back at 10%. The contractor has received progress payments for 75%
of the project. The contractor submits a request for final payment for the now
completed project. The final payment amount should be for - ANSWER-more than
$50,000.

A permit is obtained on Friday, May 1. The materials are to be delivered May 8. The
materials are needed when labor begins on May 11. It is estimated that 15 days of
labor are REQUIRED. The crew will work every day, including weekends and
holidays. The project is scheduled to be completed on June 8. How many float days
are available for the labor for this project? - ANSWER-13

Which of the following would typically be covered by a contractor's comprehensive
general liability insurance policy? - ANSWER-Damage to adjoining property from a
crane accident.

Información del documento

Subido en
4 de abril de 2024
Número de páginas
3
Escrito en
2023/2024
Tipo
Examen
Contiene
Preguntas y respuestas
$10.59

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
IMORA
4.4
(70)
Vendido
215
Seguidores
77
Artículos
5091
Última venta
1 semana hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes