Construction Project Management (COSC 353) Exam 1 – Escamilla (100% Verified Solutions)
What are the objectives of a Schedule? (5) correct answers Determine project completion time Determine Critical Activities - CP Identify which activities can be delayed Used as a tool to manage a project What is a TEMPORARY endeavor undertaken to create a unique product, service, or result? correct answers Project When is the end of a project reached? correct answers When the project objectives have been achieved, or the project is terminated. Project success is one that meets or exceeds the expectations of your _________? correct answers Stakeholders What requires the application of knowledge, skills, tools, and techniques to project activities to meet project requirements? correct answers Project Management What sets the standard for ethics and professionalism in the construction industry? correct answers AIC Code of Ethics What does AIC stand for? correct answers American Institute of Constructors What is the second-largest employer in the United States? correct answers The Construction Industry How many construction companies existed in the U.S. by 2009? correct answers 880,000 How many people were employed by the construction industry in 2009? correct answers 7.3 Million The idea is defined by the ______, developed by the _______, and produced by the ________, who then turns it over to the _________. correct answers Owner; Designer; Constructor; Owner Homeowners and Developers are considered ________ owners? correct answers Private What are some examples of Owner Representatives? correct answers Facility Managers, Outside Consultants, Building Committee, etc. What are the three categories of Owners? correct answers Private, Public, and Owner Representatives
Información del documento
- Subido en
- 6 de septiembre de 2023
- Número de páginas
- 9
- Escrito en
- 2023/2024
- Tipo
- Examen
- Contiene
- Preguntas y respuestas