Construction Project Management (COSC
353) Exam 1 - Escamilla
What are the objectives of a Schedule? (5) - Correct answer Determine project completion time
Determine Critical Activities - CP
Identify which activities can be delayed
Used as a tool to manage a project
What is a TEMPORARY endeavor undertaken to create a unique product, service, or result? -
Correct answer Project
When is the end of a project reached? - Correct answer When the project objectives have been
achieved, or the project is terminated.
Project success is one that meets or exceeds the expectations of your _________? - Correct
answer Stakeholders
What requires the application of knowledge, skills, tools, and techniques to project activities to
meet project requirements? - Correct answer Project Management
What sets the standard for ethics and professionalism in the construction industry? - Correct
answer AIC Code of Ethics
What does AIC stand for? - Correct answer American Institute of Constructors
What is the second-largest employer in the United States? - Correct answer The Construction
Industry
Construction Project Management (COSC
353) Exam 1 - Escamilla
1 / 2
How many construction companies existed in the U.S. by 2009? - Correct answer 880,000
How many people were employed by the construction industry in 2009? - Correct answer 7.3
Million
The idea is defined by the ______, developed by the _______, and produced by the ________,
who then turns it over to the _________. - Correct answer Owner; Designer; Constructor;
Owner
Homeowners and Developers are considered ________ owners? - Correct answer Private
What are some examples of Owner Representatives? - Correct answer Facility Managers,
Outside Consultants, Building Committee, etc.
What are the three categories of Owners? - Correct answer Private, Public, and Owner
Representatives
What are the two main categories of Design Professionals? - Correct answer Architects and
Engineers
Which Design Professional identifies the important elements of the design? (Physical Context,
Activities, Unique Image) - Correct answer Architect
Which Design Professional uses identifiable components and questions to be answered? -
Correct answer Engineers
Who is a professional responsible for all construction activities, whether they work as a General
Contractor, or a Construction Manager? - Correct answer Constructor
Construction Project Management (COSC
353) Exam 1 - EscamillaPowered by TCPDF (www.tcpdf.org)
2 / 2
353) Exam 1 - Escamilla
What are the objectives of a Schedule? (5) - Correct answer Determine project completion time
Determine Critical Activities - CP
Identify which activities can be delayed
Used as a tool to manage a project
What is a TEMPORARY endeavor undertaken to create a unique product, service, or result? -
Correct answer Project
When is the end of a project reached? - Correct answer When the project objectives have been
achieved, or the project is terminated.
Project success is one that meets or exceeds the expectations of your _________? - Correct
answer Stakeholders
What requires the application of knowledge, skills, tools, and techniques to project activities to
meet project requirements? - Correct answer Project Management
What sets the standard for ethics and professionalism in the construction industry? - Correct
answer AIC Code of Ethics
What does AIC stand for? - Correct answer American Institute of Constructors
What is the second-largest employer in the United States? - Correct answer The Construction
Industry
Construction Project Management (COSC
353) Exam 1 - Escamilla
1 / 2
How many construction companies existed in the U.S. by 2009? - Correct answer 880,000
How many people were employed by the construction industry in 2009? - Correct answer 7.3
Million
The idea is defined by the ______, developed by the _______, and produced by the ________,
who then turns it over to the _________. - Correct answer Owner; Designer; Constructor;
Owner
Homeowners and Developers are considered ________ owners? - Correct answer Private
What are some examples of Owner Representatives? - Correct answer Facility Managers,
Outside Consultants, Building Committee, etc.
What are the three categories of Owners? - Correct answer Private, Public, and Owner
Representatives
What are the two main categories of Design Professionals? - Correct answer Architects and
Engineers
Which Design Professional identifies the important elements of the design? (Physical Context,
Activities, Unique Image) - Correct answer Architect
Which Design Professional uses identifiable components and questions to be answered? -
Correct answer Engineers
Who is a professional responsible for all construction activities, whether they work as a General
Contractor, or a Construction Manager? - Correct answer Constructor