PMP Questions and Answers( Complete Top Solution Rated A+)
PMP Questions and Answers( Management Framework - Management Framework 1. The project life cycle is comprised of which of the following? A. Phases B. Milestones C. Estimates D. Activities - A. T he pr oject life cycle is comprised of phases. B is incorrect since milestones may exist within the project plan, but they do not comprise the project life cycle. C is wrong because estimates are not directly related to the project life cycle. Choice D, activities, comprise the phases within the project life cycle, but not the project life cycle itself. Marcy, the project manager for the ERP Project, is about to complete the Project Phase Review. The completion of a project phase is also known as which of the following?