NACE TESTED QUESTIONS AND
COMPLETE SOLUTIONS

◉ A pre-job conference should be held
Answer: after bids have been submitted and contracts signed


◉ What are the goals of a pre-job conference?
Answer: - review and discuss the scope of work
- discuss lines of communication between parties
- discuss and clarify inspector's responsibilities and authority


◉ What is one of the inspector's roles at a pre-job conference?
Answer: clarify reporting requirements


◉ According to ASTM D 4417 Method B-2014, when taking
measurements using a profile gauge , at each location make ______
Answer: ten (10) readings per location, recording the maximum
value. Determine mean for all maximum values as the reported
profile


◉ Daily reports or weekly reports should be written in ___
Answer: pen

,◉ What can inspection records be used for?
Answer: - help in resolving legal or arbitration disputes
- assist owners in the evaluation of applicator performance
- assist owners in the evaluation of inspector performance
- determine total cost of the project


◉ The inspector's log book is a personal chronicle of what
happened on a daily basis and is usually ____
Answer: retained by the inspector


◉ Generally speaking, on a typical coating project overall safety is
the responsibility of _____
Answer: a certified safety professional


◉ When applying coatings, generally high relative humidity _____
Answer: slows solvent evaporation


◉ A typical daily report should include ___ ___ ___
Answer: - description of manpower and equipment used
- explanation of work stoppages
- list of environmental conditions


◉ What is an advantage of airless spray compared to conventional
air spray?

,Answer: faster production rate


◉ What inspection challenges do you expect specific to working
inside containment?
Answer: - illumination
- control of temperature and humidity


◉ Improper atomization of the coating may cause ___ ___ ___
Answer: - uneven DFT
- dry spray
- overspray


◉ High viscosity due to low temperature should be corrected by
___ ___
Answer: - adding extra thinner
- heating the coating


◉ SSPC Technology Guide No.12 states "Surface preparation and
coating applications must have a minimum of how man candles /
lumens?
Answer: 50 foot candles (538 lumens)


◉ One major advantage of conventional spray is ___
Answer: applicator control

, ◉ When using WFT comb/gauge, the measurment should be
taken when?
Answer: immediately after the coating is applied


◉ When reporting the wet film thickness from a wet film
thickness comb/gauge you report which tooth?
Answer: the last tooth that has coating on it


◉ Solventbourne inorganic zinc primer is being applied with
airless spray to a complex bridge with difficult access for
application. The contractor is having difficulty with high DFT
resulting in mudcracking. What application method might be a
good alternative?
Answer: conventional spray


◉ An advantage of magnetic pull-off DFT banana gauge is that it is
____
Answer: intrinsically safe


◉ You must take a measurement with a dial-type magnetic pull-
off dry film thickness gauge. What is the minimum recommended
distance away from an edge that you can reliably take a
measurement?
Answer: 2.5 cm (1 inch)

Información del documento

Subido en
22 de octubre de 2026
Número de páginas
34
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$16.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Vendido
33
Seguidores
1
Artículos
20668
Última venta
16 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes